Source · Prevention of Future Deaths
Fraser Moore
Ref: 2023-0497
Date: 4 Dec 2023
Coroner: Julian Morris
Area: Inner South London
Responses identified: 0 / 2
View PDF
Inadequate CCTV coverage beyond station platforms and failure to immediately transmit footage to Route Control rooms increase the risk of undetected incidents in busy stations.
Date
4 Dec 2023
56-day deadline
29 Jan 2024 est.
Responses identified
0 of 2
Coroner's concerns
Inadequate CCTV coverage beyond station platforms and failure to immediately transmit footage to Route Control rooms increase the risk of undetected incidents in busy stations.
View full coroner's concerns
The CCTV coverage/ footage ends at the end of the station concourse on both the city and country ends. Station footage does not get sent to Route Control. On a risk-based review, the chances of incidents happening in a busy cosmopolitan station must, by footfall and surrounding populations alone, increase the risk of an event. An event that should then be looked at. In order to look at an event, I accept that current CCTV is in place within the station confines but for these stations, I do not consider that I have received sufficient evidence to persuade me that the footages should not be available immediately to the Route Control Rooms or that the coverage should not extend up or down line beyond the end of the platforms.
Report sections
Investigation and inquest
On 4 May 2020 an investigation into the death of Fraser William Moore, aged 25, was opened. The investigation concluded at the end of the inquest on 15 December 2022. The conclusion of the inquest, heard before a jury was the "inappropriate handcuffing, his unnecessary arrest, inadequate supervision of his arrest and the failing to prevent his escape." He escaped firstly onto the station concourse and then onto the railway lines at London Bridge Station.
The medical cause of death was 1a. Electrocution, 1b. Contact with live rail.
The medical cause of death was 1a. Electrocution, 1b. Contact with live rail.
Circumstances of the death
On 25 March 2020 Mr Moore had been arrested, handcuffed and was present in a carriage. He managed to exit one of the carriage doors, which was unattended and fled onto the platform. After running for a short period of time firstly up and then down the platform by moving down one side of the concourse to the other, he was running towards the country end at London Bridge Hospital. He proceeded to jump onto the track whilst still within the platform area before continuing out of the platform area towards the country. He was followed by a BTP officer. The rails were still live. The calling for the lines to be isolated occurring about the same time that maters were picked up by the signalman. Sadly, he made contact with the live rail before power could be severed. Subsequently, after the power switched off and assistance to move to his location, some distance from the platforms, he was pronounced dead at the scene.
Action should be taken
In my opinion action should be taken to look into both the extension of CCTV in busy cosmopolitan station and its passage to Route Control to help prevent future deaths and I believe you have the power to take such action.
Similar PFD reports
Related inquiry recommendations
ICL Inquiry
Replace Buried Metallic LPG Pipes
ICL Inquiry
New LPG Safety Regime
ICL Inquiry
LPG Supplier Registration
ICL Inquiry
Polyethylene Piping Research
Taylor Inquiry
Remove all spikes and inward-facing constructions from perimeter and radial fences
Taylor Inquiry
Limit perimeter fencing height to a maximum of 2.2 metres
Taylor Inquiry
Provide sufficient 1.1-metre wide gates in perimeter fences for emergency evacuation
Taylor Inquiry
Paint and mark all emergency gates in fences with "Emergency Exit
Taylor Inquiry
Keep all perimeter fence gates to pitch unlocked and open during matches
Taylor Inquiry
Annually inspect all crush barriers for corrosion; repair or replace as needed
Report details
- Reference
- 2023-0497
- Date of report
- 4 December 2023
- Coroner
- Julian Morris
- Coroner area
- Inner South London
Responses identified
Responses identified
0 of 2
2 responses not yet linked
Organisations named in PFD reports are normally expected to respond within 56 days. Deadline: 29 Jan 2024 (estimated).
Sent to
- Department for Transport
- Network Rail