Public Inquiry

Malkinson Inquiry

Ongoing · Chair: Judge Sarah Munro · Established October 2023 · Commissioned by Ministry of Justice

Non-statutory independent inquiry into the wrongful conviction of Andrew Malkinson for rape and the 17 years he spent wrongly imprisoned.

More about this inquiry

Non-statutory independent inquiry into the wrongful conviction of Andrew Malkinson for rape and the 17 years he spent wrongly imprisoned. Chaired by HHJ Sarah Munro KC, it examines the roles of Greater Manchester Police, the Crown Prosecution Service and the Criminal Cases Review Commission. The Inquiry resumed after the conclusion of Rex v Paul Quinn. Its 15 July 2026 update says Phase 2 work is continuing, including disclosure, forensic review and identifying witnesses. No final report date has been announced.

Where it stands

No report has been published yet.

Recent milestones

  • Work resumes after Quinn trial17 April 2026
  • Phase 2 begins24 February 2024
  • Chair appointed26 October 2023
Full timeline

Costs

£2,900,000

Reported cost Costs in detail

Parliament

4

mentions in Parliament Parliamentary activity

Reports and timeline

Reports

No reports listed.

Timeline

Inquiry announced

A non-statutory inquiry was announced into the wrongful conviction of Andrew Malkinson for rape and the 17 years he spent in prison.

Chair appointed

HHJ Sarah Munro KC was appointed to chair the Inquiry.

Source

Terms of Reference set

The Inquiry's Terms of Reference were published, examining the roles of Greater Manchester Police, the Crown Prosecution Service and the Criminal Cases Review Commission.

Source

Phase 2 begins

The Inquiry moved into its evidence-gathering and disclosure phase.

Work resumes after Quinn trial

The Inquiry said its work could resume following the verdicts in the trial of R v Paul Quinn, for which it had been paused.

Parliamentary activity

4 mentions since Oct 2023
2 questions 2 statements

Andrew Malkinson Inquiry

Written Question House of Commons Mike Wood · Conservative

Asked: To ask the Secretary of State for Justice, pursuant to the answer of 4 September 2025, to Question 70519, on Public Inquiries, what has been the total public cost to date of the Andrew Malkinson Inquiry.

Answered by Ministry of Justice: The total cost of the Malkinson Inquiry from its commencement in October 2023, up to the end of the financial year 2025/26 is £2.9 million.

Ministry of Justice: Public Appointments

Written Question House of Commons Charlie Dewhirst · Conservative

Asked: To ask the Secretary of State for Justice, what the (a) name, (b) job title, (c) annual remuneration, (d) time commitment and (e) expected end date is for each direct ministerial appointment in his Department.

Answered by Ministry of Justice: The Ministry of Justice makes information on its direct ministerial appointments available in line with Cabinet Office guidance on transparency. This information is available on GOV.UK and kept under review to ensure it is up to date. Name(s) Job Title Press Release Kate Green; Dr Tom McNeil; Katy Swaine Williams; Dr Shona Minson; Bernie Bowen-Thomson; Michaela Booth; Anne Fox; Lady …

Andrew Malkinson Inquiry Announcement

Written Ministerial Statement House of Lords Lord Bellamy · Conservative

Statement: My right honourable friend the Lord Chancellor and Secretary of State for Justice has made the following statement:'In August 2023, I announced that the Ministry of Justice would establish a non-statutory independent inquiry into the issues raised by the miscarriage of justice suffered by Andrew …

Andrew Malkinson Inquiry Announcement

Written Ministerial Statement House of Commons Alex Chalk · Conservative

Statement: In August 2023, I announced that the Ministry of Justice would establish a non-statutory independent inquiry into the issues raised by the miscarriage of justice suffered by Andrew Malkinson. Mr Malkinson deserves thorough answers as to how and why this miscarriage of justice took so …

View all 4 mentions →

Key facts

Duration (ongoing): 2 years, 11 months Total reported cost: £2.9m