Grenfell Tower Inquiry. Read indexed debates, questions, statements and early day motions, with links to the original parliamentary records.

202 indexed mentions for this inquiry Earliest recorded mention: 21 June 2017

Parliamentary mentions

202 matching mentions · newest first

High Rise Flats: Insulation

Written Question House of Lords
Baroness Finlay of Llandaff · Crossbench Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

To ask Her Majesty's Government what is the maximum level of fine they can impose on freeholders of flat blocks where dangerous cladding has not been removed; and how many such fines have been imposed since the Grenfell Tower Inquiry started.

Government answer

Answering body: Ministry of Housing, Communities and Local Government

Government itself cannot impose fines but where building owners are failing to make acceptable progress in removing unsafe cladding then they should expect enforcement action by local authorities or Fire and Rescue Authorities. We have established a Joint Inspection Team to support local authorities in taking enforcement action where building owners are refusing to remediate high-rise buildings with unsafe cladding or are not making acceptable progress. Local authorities have a duty to take enforcement action under the Housing Act 2004 if they find the most serious ‘category 1’ hazards on residential premises and failure to comply with this can result in a financial penalty of up to £30,000 or prosecution in the Magistrates’ Court, which may result in a unlimited fine on conviction.

The Fire Safety Bill will also clarify that the Regulatory Reform (Fire Safety) Order 2005 (the ‘Fire Safety Order’) applies to external wall systems and will put beyond doubt that Fire and Rescue Authorities can enforce against and where necessary, pursue prosecution if Responsible Persons or those otherwise responsible under the Fire Safety Order fail to take appropriate fire safety measures with regards to unsafe cladding in multi-occupied residential buildings. The highest financial penalty that can be imposed for non-compliance with the Fire Safety Order is an unlimited fine. It is for the Court to decide on a case-by-case basis what financial penalty should be allocated. Details of enforcement action taken or being taken by local authorities and Fire and Rescue Authorities in regard to the buildings with unsafe Aluminium Composite Material (ACM) cladding can be found on the Building Safety Programme Monthly Data Release which is available (attached) at: https://www.gov.uk/guidance/aluminium-composite-material-cladding#acm-remediation-data .

Original parliamentary record

Appointment of Additional Grenfell Tower Inquiry Panel Member

Written Ministerial Statement House of Lords
Baroness Evans of Bowes Park · Conservative Answering body: Leader of the House of Lords
Parliamentary excerpt

My Rt Hon Friend the Prime Minister has made the following statement: The fire in Grenfell Tower on 14 June 2017 was an unimaginable tragedy that should never have happened. The Government set up the Grenfell Tower Inquiry to get to the truth about what happened and to deliver justice for victims, survivors, bereaved families and the wider community. Ensuring that such a terrible tragedy can never happen again remains a priority for this Government. In February this year, I announced my inten...

Recorded statement

Answering body: Leader of the House of Lords

My Rt Hon Friend the Prime Minister has made the following statement:

The fire in Grenfell Tower on 14 June 2017 was an unimaginable tragedy that should never have happened.

The Government set up the Grenfell Tower Inquiry to get to the truth about what happened and to deliver justice for victims, survivors, bereaved families and the wider community.

Ensuring that such a terrible tragedy can never happen again remains a priority for this Government.

In February this year, I announced my intention to appoint an additional panel member to the Grenfell Tower Inquiry. Section 7(1)(b) of the Inquiries Act 2005 allows me to appoint panel members to the Inquiry panel at any time during the Inquiry. In appointing a panel member, section 8(1)(a) and (b) of the Inquiries Act 2005 require me to ensure that the Inquiry panel (considered as a whole) has the necessary expertise to undertake the Inquiry, and to consider the need for balance (considered against the background of the terms of reference) in the composition of the panel.

Phase 2 of the Inquiry is the largest phase in terms of the number and range of issues to be considered, and given the diversity of issues, and the expertise already available to the Inquiry, I am pleased to appoint Ali Akbor OBE as the Inquiry’s third panel member.

Ali is currently the CEO of Unity Homes and Enterprise, a leading housing association supporting sustainable and diverse neighbourhoods in West Yorkshire. Prior to his role at Unity, Ali was finance director for the Community and Social Services Directorate at the City of Salford. In December 2019, he was awarded an OBE for services to the community in Leeds. His knowledge of, and professional expertise in social housing, local government and community engagement are highly relevant skills and experience which will add great value to the Inquiry panel.

I am confident that Ali’s appointment will ensure that the Inquiry panel has the diversity of skills and expertise necessary for the scope and complexity of issues to be addressed by Phase 2 of its work.

I wrote to the Chair of the Inquiry, Sir Martin Moore-Bick, on 12 October informing him of my decision and to seek his consent to the appointment in accordance with section 7(2)(b) of the Inquiries Act 2005. Sir Martin replied on 13 October consenting to the appointment.

Ali will read into the work of the Inquiry while he formally steps back from his role at Unity and will join the Inquiry panel on 2 November for the start of module 2 of its work. It is intended that Ali will sit for the duration of the Inquiry and, alongside his two fellow panel members, will be jointly responsible for the whole of the Inquiry's Phase 2 work.

Our exchange of letters can be found on gov.uk.

Original parliamentary record

Launching a review of the Police and Crime Commissioner model

Written Ministerial Statement House of Commons
Kit Malthouse · Conservative Answering body: Home Office
Parliamentary excerpt

I wish to set out to the House details of a review into the role of Police and Crime Commissioners. The Government’s manifesto committed to strengthening the accountability of PCCs and expanding their role. Police and Crime Commissioners were introduced in 2012 to give the public a direct say over policing in their area. Since coming into post, they have brought real local accountability to policing and are working to give local communities a stronger voice. After eight years it is right that...

Recorded statement

Answering body: Home Office

I wish to set out to the House details of a review into the role of Police and Crime Commissioners.

The Government’s manifesto committed to strengthening the accountability of PCCs and expanding their role. Police and Crime Commissioners were introduced in 2012 to give the public a direct say over policing in their area. Since coming into post, they have brought real local accountability to policing and are working to give local communities a stronger voice.

After eight years it is right that we step back and consider how we can continue to evolve the PCC model. It is important that PCCs are strong, visible leaders in the fight against crime and have the legitimacy and tools to hold their police forces to account effectively.

To deliver this commitment, I am today announcing a two-part internal review into the role of PCCs.

Part one will commence in late July and report to the Home Secretary and myself by October 2020. It will be focussed on changes required to strengthen the model which, where possible, can be delivered ahead of the 2021 PCC elections. In particular, it will: consider how to strengthen the accountability, resilience, legitimacy and scrutiny mechanisms of the existing model to drive up standards; identify and share best practice across the sector; and examine the effectiveness of the relationship between PCCs and Chief Constables and the checks and balances currently in place.

We will also use part one of the review to help us map out our longer-term ambition for the expansion of the PCC role. In relation to fire, the Government is clear that further reform of fire and rescue services is required in order to respond to the recommendations from Phase 1 of the Grenfell Tower Inquiry and to build on the findings from Sir Tom Winsor’s State of Fire and Rescue Report, both of which demonstrate the clear challenges and improvements required in professionalism, people and governance. The review will consider further options and opportunities to strengthen fire governance and accountability, drawing on the lessons from the first cycle of fire governance transfers to PCCs.

The review will also be fully aligned with the Government’s commitment to expand the benefits of devolution across England through the Local Recovery and Devolution White Paper. Mayors of Combined Authorities should be powerful local figures with the ability to drive public safety, as well as economic growth and local recovery. We plan to develop the role of PCCs with that longer-term trajectory in mind, building on the models in London and Greater Manchester.

I would like to be clear that neither Part one or Part two of the review will consider a wholly new governance model for policing or examine the 43 police force model.

An Advisory Group will support part one of the review, comprising senior external stakeholders with expertise in the policing and fire sectors. It will also be important that the public’s views on those who represent them in policing are heard and the review team will seek to engage a sample of citizens and local and national victims’ groups as appropriate.

Part two of the review will commence after the 2021 elections and will allow us to consider further ways to strengthen and expand the role of PCCs, including the role PCCs play in tackling re-offending to help reduce crime. It will focus on longer-term reforms and the potential for wider efficiencies to be made within the system with a view to implementation ahead of the 2024 elections.

I will place a copy of the Terms of Reference for part one of the review in the Libraries of both Houses.

Original parliamentary record

Launching a review of the Police and Crime Commissioner model

Written Ministerial Statement House of Lords
Baroness Williams of Trafford · Conservative Answering body: Home Office
Parliamentary excerpt

My hon Friend the Minister of State for Crime, Policing and the Fire Service (Kit Malthouse) has today made the following Written Ministerial Statement:I wish to set out to the House details of a review into the role of Police and Crime Commissioners. The Government’s manifesto committed to strengthening the accountability of PCCs and expanding their role. Police and Crime Commissioners were introduced in 2012 to give the public a direct say over policing in their area. Since coming into post...

Recorded statement

Answering body: Home Office

My hon Friend the Minister of State for Crime, Policing and the Fire Service (Kit Malthouse) has today made the following Written Ministerial Statement:

I wish to set out to the House details of a review into the role of Police and Crime Commissioners.

The Government’s manifesto committed to strengthening the accountability of PCCs and expanding their role. Police and Crime Commissioners were introduced in 2012 to give the public a direct say over policing in their area. Since coming into post, they have brought real local accountability to policing and are working to give local communities a stronger voice.

After eight years it is right that we step back and consider how we can continue to evolve the PCC model. It is important that PCCs are strong, visible leaders in the fight against crime and have the legitimacy and tools to hold their police forces to account effectively.

To deliver this commitment, I am today announcing a two-part internal review into the role of PCCs.

Part one will commence in late July and report to the Home Secretary and myself by October 2020. It will be focussed on changes required to strengthen the model which, where possible, can be delivered ahead of the 2021 PCC elections. In particular, it will: consider how to strengthen the accountability, resilience, legitimacy and scrutiny mechanisms of the existing model to drive up standards; identify and share best practice across the sector; and examine the effectiveness of the relationship between PCCs and Chief Constables and the checks and balances currently in place.

We will also use part one of the review to help us map out our longer-term ambition for the expansion of the PCC role. In relation to fire, the Government is clear that further reform of fire and rescue services is required in order to respond to the recommendations from Phase 1 of the Grenfell Tower Inquiry and to build on the findings from Sir Tom Winsor’s State of Fire and Rescue Report, both of which demonstrate the clear challenges and improvements required in professionalism, people and governance. The review will consider further options and opportunities to strengthen fire governance and accountability, drawing on the lessons from the first cycle of fire governance transfers to PCCs.

The review will also be fully aligned with the Government’s commitment to expand the benefits of devolution across England through the Local Recovery and Devolution White Paper. Mayors of Combined Authorities should be powerful local figures with the ability to drive public safety, as well as economic growth and local recovery. We plan to develop the role of PCCs with that longer-term trajectory in mind, building on the models in London and Greater Manchester.

I would like to be clear that neither Part one or Part two of the review will consider a wholly new governance model for policing or examine the 43 police force model.

An Advisory Group will support part one of the review, comprising senior external stakeholders with expertise in the policing and fire sectors. It will also be important that the public’s views on those who represent them in policing are heard and the review team will seek to engage a sample of citizens and local and national victims’ groups as appropriate.

Part two of the review will commence after the 2021 elections and will allow us to consider further ways to strengthen and expand the role of PCCs, including the role PCCs play in tackling re-offending to help reduce crime. It will focus on longer-term reforms and the potential for wider efficiencies to be made within the system with a view to implementation ahead of the 2024 elections.

I will place a copy of the Terms of Reference for part one of the review in the Libraries of both Houses.

Original parliamentary record

Building Safety update

Written Ministerial Statement House of Commons
Robert Jenrick · Conservative Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

I would like to update Parliament on the Government’s progress in overhauling the building and fire safety system, as part of our unwavering commitment to ensuring that people, and the buildings they live in, are safe.Building safetyWe must never forget the seventy two people who lost their lives as a result of the Grenfell Tower tragedy. Countless lives were torn apart by that tragedy and we owe it to the deceased, the bereaved, the survivors, and the residents of all high-rise buildings to ...

Recorded statement

Answering body: Ministry of Housing, Communities and Local Government

I would like to update Parliament on the Government’s progress in overhauling the building and fire safety system, as part of our unwavering commitment to ensuring that people, and the buildings they live in, are safe.

Building safety

We must never forget the seventy two people who lost their lives as a result of the Grenfell Tower tragedy. Countless lives were torn apart by that tragedy and we owe it to the deceased, the bereaved, the survivors, and the residents of all high-rise buildings to ensure that we do all we can to prevent a repeat of events like that fateful night occurring again.

We promised to overhaul the system and to establish a national building safety regulator at its heart. Today I am pleased to be making a significant step towards that fundamental reform by publishing the draft Building Safety Bill for pre-legislative scrutiny, before the final Bill is brought forward to Parliament.

The Bill will establish the regulator in the Health and Safety Executive (HSE) and give it significant powers to improve safety and performance across the built environment, especially in higher-risk buildings.

These reforms will improve safety and performance standards across all buildings. However, certain buildings warrant even closer oversight because the potential for significant consequences should a fire spread or the structure fail. It is right that we have a more stringent regime where the risk is deemed greatest, to protect the greatest number of people. Initially the scope of the more stringent regime will apply to multi-occupied residential buildings of 18 metres or more in height or more than six storeys, whichever is reached first. We have designed the new regime so its scope can be changed if the evidence base or operational experience suggest it should.

The Bill will provide a stronger framework to make sure those responsible for managing building safety risks in higher-risk buildings are held to account, with stronger enforcement powers and sanctions where those rules are not followed. It will also ensure that the residents of high-rise buildings have a stronger voice, alongside giving them better access to safety information about their building, clarifying their rights and providing recourse to raise safety concerns directly to the regulator.

The draft Bill applies to England only with the exception of the policies to require developers to belong to a New Homes Ombudsman scheme, strengthen the oversight of the construction products regulatory regime, and allow the Architects Registration Board (ARB) to monitor the competence of architects. Further detailed analysis of the territorial extent is provided in the Explanatory Notes.

Building safety financing

The Government is clear that it is unacceptable for leaseholders to have to worry about the cost of fixing historic safety defects in their buildings that they didn’t cause.

The draft Bill proposes a new ‘building safety charge’, which will give leaseholders greater transparency around costs incurred in maintaining a safe building. We want these to be fair and proportionate, which is why I have deliberately included numerous powers in the Bill that will enable us to limit the building safety costs that can be re-charged to leaseholders.

This is a topic that we are particularly committed to developing further throughout the process of scrutiny and as the Bill is finalised for introduction. I have asked Michael Wade, senior adviser to the Cabinet Office, to accelerate this work with leaseholders and the financial sector. We must remove barriers to fixing historic defects and identify financing solutions that protect leaseholders from unaffordable costs; but we must also ensure that the bill does not fall on tax payers. We will update on any further measures required before the final Bill is introduced to Parliament.

Establishing the Building Safety Regulator

As I announced in January, the HSE is establishing the regulator in shadow form, and I am today announcing that I have set aside £16.4 million in this financial year for HSE to recruit the people and develop the capabilities that will enable the regulator to hit the ground running once its powers come into effect.

HSE has a strong track record of improving safety and fostering a safety-first culture within the construction and major hazards industries, and will draw on years of experience to deliver results quickly and effectively. As shadow regulator, HSE is playing an increasingly important role in the Government’s Building Safety Programme: it is supporting work on how to identify higher-risk buildings; supporting work by the National Fire Chiefs Council to assess the fire risk in every high-rise residential building by end 2021; and supporting work with early adopters in the construction industry, social landlords and local government to trial the new regime, and to promote culture change across the industry. I am today announcing that HSE will also take over as chair of the Joint Regulators’ Group, which advises the Government on ways to strengthen the regulatory regime; and will take over the Independent Expert Advisory Panel, which advises the Government on fire safety in high-rise residential buildings.

Over coming months, the shadow regulator will engage with and advise residents, building owners, the construction industry and other regulators on how the new system will operate, what it will mean for them, and what they should do now to make their buildings safe and prepare for the new regime. In the Autumn, we will kick off work to appoint the first national Chief Inspector of Buildings, who will lead the new regulator.

We, and the public, expect industry to manage building safety risks now and prepare to fulfil their duties when this new regime comes into effect. The public expects and demands industry to implement these reforms with conviction and speed. The new Building Safety Regulator stands ready to work hand in hand with industry to bring about a culture change that prioritises residents and their safety.

Fire safety reforms

The Home Office is also today publishing a Fire Safety Consultation, which sets out proposals to: strengthen the Regulatory Reform (Fire Safety) Order 2005 – the Fire Safety Order – and improve compliance for all regulated buildings; implement the Grenfell Tower Inquiry Phase 1 report recommendations for multi-occupied residential buildings which require a change in law; and, seeks views on the effectiveness of the arrangements for consultation and information sharing between building control bodies and fire and rescue authorities in relation to building work. This is alongside a commitment to overhaul the Fire Safety Order’s supporting guidance.

Proposals for multi-occupied residential buildings, mostly high-rise buildings, include prescribing in law the frequency of checks of fire doors; that Responsible Persons (RPs) carry out inspections of other key fire-fighting equipment, not just lifts designed to be used by firefighters; and that RPs provide information to residents including in relation to fire safety (including evacuation and other specific information) in an accessible format.

Our proposals go beyond the Grenfell Tower Inquiry’s recommendations in several areas. In others, our proposals prioritise residents’ safety in a way that is practical, proportionate and effective to the risks the Inquiry has identified. The Government wants to listen to the views of those who have experience of these matters, including those who have been personally affected by the Grenfell Tower tragedy. The proposals set out in the Home Office consultation will further deliver the Government’s objective to improve building and fire safety in all regulated premises where people live, stay or work.

Construction products

The Bill also enables us to progress our commitment to radically strengthen oversight of the regulatory regime for construction products. The bill will make sure a wider range of construction products are subject to strengthened safety regulations. It will also strengthen the powers available to the Government, paving the way to create a new national regulatory function that will have oversight of the construction products regulation. The Government is developing options for how this new national regulatory function could be implemented.

Other housing measures

The draft Bill also contains measures to protect the rights of all new build homebuyers by requiring developers to belong to the New Homes Ombudsman. It also includes new measures that will make access to redress swifter and more effective for all social housing residents.

Pre-legislative scrutiny

These are extensive reforms that it is incumbent on us all to get right. The Building Safety Bill is a large and complex piece of legislation, reflecting the scale of the reforms needed. In this spirit, I am publishing the Bill in draft form to ensure it receives the due and proper consideration it deserves through pre-legislative scrutiny from Parliament, from industry, from regulatory bodies, and from residents. I want to thank those that have helped shape the legislation so far, including those who contributed to the ‘Building a Safer Future’ consultation and who have engaged in various forums with my department. I now encourage colleagues from across both Houses to engage wholeheartedly in strengthening these proposals so that together we can further improve the legislation and deliver greater safety for residents.

I will deposit copies of the draft Building Safety Bill, Delegated Powers Memorandum and Impact Assessment in the libraries of both Houses. A copy of the full Fire Safety Consultation and its Impact Assessment will also be deposited in the libraries of both Houses.

Original parliamentary record

Building Safety update

Written Ministerial Statement House of Lords
Lord Greenhalgh · Conservative Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

My Rt Hon. Friend, the Secretary of State for the Ministry of Housing, Communities and Local Government (Robert Jenrick) has today made the following Written Ministerial Statement:I would like to update Parliament on the Government’s progress in overhauling the building and fire safety system, as part of our unwavering commitment to ensuring that people, and the buildings they live in, are safe.Building safetyWe must never forget the seventy two people who lost their lives as a result of the ...

Recorded statement

Answering body: Ministry of Housing, Communities and Local Government

My Rt Hon. Friend, the Secretary of State for the Ministry of Housing, Communities and Local Government (Robert Jenrick) has today made the following Written Ministerial Statement:

I would like to update Parliament on the Government’s progress in overhauling the building and fire safety system, as part of our unwavering commitment to ensuring that people, and the buildings they live in, are safe.

Building safety

We must never forget the seventy two people who lost their lives as a result of the Grenfell Tower tragedy. Countless lives were torn apart by that tragedy and we owe it to the deceased, the bereaved, the survivors, and the residents of all high-rise buildings to ensure that we do all we can to prevent a repeat of events like that fateful night occurring again.

We promised to overhaul the system and to establish a national building safety regulator at its heart. Today I am pleased to be making a significant step towards that fundamental reform by publishing the draft Building Safety Bill for pre-legislative scrutiny, before the final Bill is brought forward to Parliament.

The Bill will establish the regulator in the Health and Safety Executive (HSE) and give it significant powers to improve safety and performance across the built environment, especially in higher-risk buildings.

These reforms will improve safety and performance standards across all buildings. However, certain buildings warrant even closer oversight because the potential for significant consequences should a fire spread or the structure fail. It is right that we have a more stringent regime where the risk is deemed greatest, to protect the greatest number of people. Initially the scope of the more stringent regime will apply to multi-occupied residential buildings of 18 metres or more in height or more than six storeys, whichever is reached first. We have designed the new regime so its scope can be changed if the evidence base or operational experience suggest it should.

The Bill will provide a stronger framework to make sure those responsible for managing building safety risks in higher-risk buildings are held to account, with stronger enforcement powers and sanctions where those rules are not followed. It will also ensure that the residents of high-rise buildings have a stronger voice, alongside giving them better access to safety information about their building, clarifying their rights and providing recourse to raise safety concerns directly to the regulator.

The draft Bill applies to England only with the exception of the policies to require developers to belong to a New Homes Ombudsman scheme, strengthen the oversight of the construction products regulatory regime, and allow the Architects Registration Board (ARB) to monitor the competence of architects. Further detailed analysis of the territorial extent is provided in the Explanatory Notes.

Building safety financing

The Government is clear that it is unacceptable for leaseholders to have to worry about the cost of fixing historic safety defects in their buildings that they didn’t cause.

The draft Bill proposes a new ‘building safety charge’, which will give leaseholders greater transparency around costs incurred in maintaining a safe building. We want these to be fair and proportionate, which is why I have deliberately included numerous powers in the Bill that will enable us to limit the building safety costs that can be re-charged to leaseholders.

This is a topic that we are particularly committed to developing further throughout the process of scrutiny and as the Bill is finalised for introduction. I have asked Michael Wade, senior adviser to the Cabinet Office, to accelerate this work with leaseholders and the financial sector. We must remove barriers to fixing historic defects and identify financing solutions that protect leaseholders from unaffordable costs; but we must also ensure that the bill does not fall on tax payers. We will update on any further measures required before the final Bill is introduced to Parliament.

Establishing the Building Safety Regulator

As I announced in January, the HSE is establishing the regulator in shadow form, and I am today announcing that I have set aside £16.4 million in this financial year for HSE to recruit the people and develop the capabilities that will enable the regulator to hit the ground running once its powers come into effect.

HSE has a strong track record of improving safety and fostering a safety-first culture within the construction and major hazards industries, and will draw on years of experience to deliver results quickly and effectively. As shadow regulator, HSE is playing an increasingly important role in the Government’s Building Safety Programme: it is supporting work on how to identify higher-risk buildings; supporting work by the National Fire Chiefs Council to assess the fire risk in every high-rise residential building by end 2021; and supporting work with early adopters in the construction industry, social landlords and local government to trial the new regime, and to promote culture change across the industry. I am today announcing that HSE will also take over as chair of the Joint Regulators’ Group, which advises the Government on ways to strengthen the regulatory regime; and will take over the Independent Expert Advisory Panel, which advises the Government on fire safety in high-rise residential buildings.

Over coming months, the shadow regulator will engage with and advise residents, building owners, the construction industry and other regulators on how the new system will operate, what it will mean for them, and what they should do now to make their buildings safe and prepare for the new regime. In the Autumn, we will kick off work to appoint the first national Chief Inspector of Buildings, who will lead the new regulator.

We, and the public, expect industry to manage building safety risks now and prepare to fulfil their duties when this new regime comes into effect. The public expects and demands industry to implement these reforms with conviction and speed. The new Building Safety Regulator stands ready to work hand in hand with industry to bring about a culture change that prioritises residents and their safety.

Fire safety reforms

The Home Office is also today publishing a Fire Safety Consultation, which sets out proposals to: strengthen the Regulatory Reform (Fire Safety) Order 2005 – the Fire Safety Order – and improve compliance for all regulated buildings; implement the Grenfell Tower Inquiry Phase 1 report recommendations for multi-occupied residential buildings which require a change in law; and, seeks views on the effectiveness of the arrangements for consultation and information sharing between building control bodies and fire and rescue authorities in relation to building work. This is alongside a commitment to overhaul the Fire Safety Order’s supporting guidance.

Proposals for multi-occupied residential buildings, mostly high-rise buildings, include prescribing in law the frequency of checks of fire doors; that Responsible Persons (RPs) carry out inspections of other key fire-fighting equipment, not just lifts designed to be used by firefighters; and that RPs provide information to residents including in relation to fire safety (including evacuation and other specific information) in an accessible format.

Our proposals go beyond the Grenfell Tower Inquiry’s recommendations in several areas. In others, our proposals prioritise residents’ safety in a way that is practical, proportionate and effective to the risks the Inquiry has identified. The Government wants to listen to the views of those who have experience of these matters, including those who have been personally affected by the Grenfell Tower tragedy. The proposals set out in the Home Office consultation will further deliver the Government’s objective to improve building and fire safety in all regulated premises where people live, stay or work.

Construction products

The Bill also enables us to progress our commitment to radically strengthen oversight of the regulatory regime for construction products. The bill will make sure a wider range of construction products are subject to strengthened safety regulations. It will also strengthen the powers available to the Government, paving the way to create a new national regulatory function that will have oversight of the construction products regulation. The Government is developing options for how this new national regulatory function could be implemented.

Other housing measures

The draft Bill also contains measures to protect the rights of all new build homebuyers by requiring developers to belong to the New Homes Ombudsman. It also includes new measures that will make access to redress swifter and more effective for all social housing residents.

Pre-legislative scrutiny

These are extensive reforms that it is incumbent on us all to get right. The Building Safety Bill is a large and complex piece of legislation, reflecting the scale of the reforms needed. In this spirit, I am publishing the Bill in draft form to ensure it receives the due and proper consideration it deserves through pre-legislative scrutiny from Parliament, from industry, from regulatory bodies, and from residents. I want to thank those that have helped shape the legislation so far, including those who contributed to the ‘Building a Safer Future’ consultation and who have engaged in various forums with my department. I now encourage colleagues from across both Houses to engage wholeheartedly in strengthening these proposals so that together we can further improve the legislation and deliver greater safety for residents.

I will deposit copies of the draft Building Safety Bill, Delegated Powers Memorandum and Impact Assessment in the libraries of both Houses. A copy of the full Fire Safety Consultation and its Impact Assessment will also be deposited in the libraries of both Houses.

Original parliamentary record

Grenfell Update

Written Ministerial Statement House of Lords
Lord Greenhalgh · Conservative Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

My Rt Hon. Friend, the Secretary of State for the Ministry of Housing, Communities and Local Government (Robert Jenrick) has today made the following Written Ministerial Statement:On 30 October 2019 Phase 1 of the Grenfell Tower Inquiry, which focused on how the fire started and spread and the emergency response, concluded with the publication of the Phase 1 report. In January 2020 the Government reaffirmed the acceptance, first given on the day of publication, to accept in principle, all the...

Recorded statement

Answering body: Ministry of Housing, Communities and Local Government

My Rt Hon. Friend, the Secretary of State for the Ministry of Housing, Communities and Local Government (Robert Jenrick) has today made the following Written Ministerial Statement:

On 30 October 2019 Phase 1 of the Grenfell Tower Inquiry, which focused on how the fire started and spread and the emergency response, concluded with the publication of the Phase 1 report. In January 2020 the Government reaffirmed the acceptance, first given on the day of publication, to accept in principle, all the recommendations that Sir Martin Moore-Bick made for central government in that report.

Six months on from the publication of the Government’s response to the Phase 1 report, I would like to update Parliament on the Government’s progress at turning our commitments into real and lasting change to building and fire safety.

The Grenfell fire was an unimaginable tragedy that must never be allowed to happen again. Even in these unprecedented times, the Government’s commitment to implementing the Inquiry’s recommendations, as a priority, remains unchanged. As does the Government’s commitment to ensuring those most affected, the bereaved and survivors – who have displayed such remarkable courage, resilience and dignity – continue to be engaged in discussions about policy development.

Ban on the use of combustible materials

The Inquiry’s report was clear that the use of Aluminium Composite Material (ACM) rainscreen cladding and combustible insulation on the exterior of the Tower was the defining factor in the rapid spread of the fire. The Government introduced regulations in December 2018 that banned the use of combustible materials in and on the external walls of specific types of new high-rise buildings. A public consultation was held between January and May 2020, to further explore and refine the scope of that ban – including a proposal to ban the use of ACM with unmodified polyethylene core and similar materials on all buildings in England. We are analysing feedback and will be publishing a response in due course.

Remediation

Since the Grenfell Tower fire, the Ministry of Housing, Communities and Local Government (MHCLG) and the Home Office (HO) have identified over 450 buildings with unsafe ACM cladding, and we have worked with local authorities and fire and rescue authorities to ensure that appropriate interim safety measures are in place, while these buildings undergo remediation.

In March this year the Government announced that it will provide £1 billion to fund the removal and replacement of unsafe non-ACM cladding systems. This is in addition to the £600 million which Government has made available for remediation of the highest risk ACM cladding. The prospectus for this fund was launched last month and sets out the buildings and non-ACM cladding systems that are eligible for funding and registration is now open for potential applicants, in advance of the full application process opening by the end of July 2020. More information on the Fund Prospectus can be found here: https://www.gov.uk/guidance/remediation-of-non-acm-buildings#prospectus---outlining-eligibility-for-the-fund.

This fund will meet the cost of remediating unsafe non-ACM cladding systems where building owners (or other entities legally responsible for making buildings safe) are unable to do so. Government are also providing additional, specialist project management capability to building owners or managing agents to speed up the development and implementation of building plans.

The Fire Protection Board

The Government has also established a Fire Protection Board, chaired by the National Fire Chiefs Council (NFCC), to provide greater assurance to central government of Fire and Rescue Service protection activity. The Board is leading a Building Risk Review Programme, supported by government funding to ensure that all high-rise residential buildings of 18m or above are inspected or reviewed by the end of 2021. We are also using a proportion of the additional £20m secured for fire and rescue services in the recent Budget to further support an uplift in protection capability.

Stay Put

At the end of last year, a joint HO and MHCLG steering group was set up to support a technical review of stay put. There are three strands to this work: an evidence review, assessing academic evidence on methods of evacuation; operational research to test evacuation strategies; and building design research. The first stage of this work has been commissioned and is underway whilst preliminary work is being carried out on the other strands.

Building safety

At the heart of the Government’s radical reforms to building safety is the new Building Safety Regulator, which we are establishing within the Health and Safety Executive. The Government set out plans in our response to the ‘Building a Safer Future’ consultation for the biggest change in building safety for a generation.

The new regulator will be responsible for implementing and enforcing a more stringent regulatory regime for higher risk buildings, as well as providing wider and stronger oversight of safety and performance across all buildings and increasing the competence of those working on building safety. This work complements the establishment of a new construction products regulatory role to strengthen national oversight and effectively enforce the new regulatory regime.

The Government will soon be publishing the draft Building Safety Bill for scrutiny before it is introduced in Parliament. This Bill will put in place this new and enhanced regulatory regimes for building safety and construction products, and ensure residents have a stronger voice.

In April, the Government published a workplan detailing the next steps for the wider review of Approved Document B, following the technical review that was started in December 2018. Research will be carried out in areas such as means of escape, compartmentation and toxicity. This work will build on the changes we have published in an update to Approved Document B last month, so that sprinklers and wayfinding signage will be provided in all new blocks of flats above 11 metres. The Government is also working with the NFCC on further tests of evacuation with a view to including guidance on provision of these systems in a later update to Approved Document B.

Fire Safety Bill

The Inquiry’s Phase 1 report also called for new duties on building owners and managers to share technical information with fire and rescue services and undertake regular inspections of flat entrance doors. It is our intention to take forward these recommendations for existing buildings under the Regulatory Reform (Fire Safety) Order 2005 underpinned by the changes being introduced through the Fire Safety Bill.

The Fire Safety Bill, which was introduced in March and received cross-party support, clarifies that the scope of the Fire Safety Order covers external walls (including cladding and balconies) and flat entrance doors in multi-occupied residential buildings. It provides a firm foundation upon which to bring forward secondary legislation to implement the recommendations that require further changes to the law. The Bill is a significant further step to ensure better identification and management of fire safety risks in such buildings.

It is important that the Government’s response to the Inquiry’s recommendations has the support of those with experience in these matters, and those most affected by them. To ensure their views inform our response, a public consultation will be issued soon setting out the Government’s proposed approach to the remaining recommendations that call for legislative change.

Fire and Rescue Services

Many of the recommendations within the Inquiry’s Phase 1 report were directed at non-Government organisations that are equally committed to the reforms. The report was clear that the London Fire Brigade (LFB) must learn and change to restore public confidence. Our request for regular progress reports from the LFB setting out how they are translating the recommendations into action are a key part of retaining focus and momentum on the need for change.

There remains much to do, but the HO is already seeing a commitment to revised policy and procedures backed up by the use of better equipment and technology to support high-rise fire fighting and fire fighting in London more broadly. The pandemic has created many challenges, but it has not affected the LFB’s commitment to implementing the Inquiry’s Phase 1 recommendations.

It is important that the lessons from Grenfell are learned beyond London. This is why the NFCC is working to ensure that the Phase 1 recommendations are implemented across all fire and rescue services. The HO is working closely with the NFCC on an improvement plan to help it drive real change across the sector.

In the three years since the Grenfell Tower fire, the Government has remained steadfast in its commitment to driving forward both cultural and legislative change so that no such tragedy can ever be allowed to happen again. Through implementation of the reforms highlighted in this statement, and wider work of Government and our stakeholders, we will move from the conditions that allowed a tragedy like the fire at Grenfell Tower to occur almost three years ago, to a system which ensures developers and building owners demonstrate greater responsibility for the safety of residents and which allows local authorities and fire and rescue authorities to enforce this. The Government is firmly committed to ensuring all residents are safe in their homes, now and in the future.

Original parliamentary record

Grenfell Update

Written Ministerial Statement House of Commons
Robert Jenrick · Conservative Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

On 30 October 2019 Phase 1 of the Grenfell Tower Inquiry, which focused on how the fire started and spread and the emergency response, concluded with the publication of the Phase 1 report. In January 2020 the Government reaffirmed the acceptance, first given on the day of publication, to accept in principle, all the recommendations that Sir Martin Moore-Bick made for central government in that report.Six months on from the publication of the Government’s response to the Phase 1 report, I woul...

Recorded statement

Answering body: Ministry of Housing, Communities and Local Government

On 30 October 2019 Phase 1 of the Grenfell Tower Inquiry, which focused on how the fire started and spread and the emergency response, concluded with the publication of the Phase 1 report. In January 2020 the Government reaffirmed the acceptance, first given on the day of publication, to accept in principle, all the recommendations that Sir Martin Moore-Bick made for central government in that report.

Six months on from the publication of the Government’s response to the Phase 1 report, I would like to update Parliament on the Government’s progress at turning our commitments into real and lasting change to building and fire safety.

The Grenfell fire was an unimaginable tragedy that must never be allowed to happen again. Even in these unprecedented times, the Government’s commitment to implementing the Inquiry’s recommendations, as a priority, remains unchanged. As does the Government’s commitment to ensuring those most affected, the bereaved and survivors – who have displayed such remarkable courage, resilience and dignity – continue to be engaged in discussions about policy development.

Ban on the use of combustible materials

The Inquiry’s report was clear that the use of Aluminium Composite Material (ACM) rainscreen cladding and combustible insulation on the exterior of the Tower was the defining factor in the rapid spread of the fire. The Government introduced regulations in December 2018 that banned the use of combustible materials in and on the external walls of specific types of new high-rise buildings. A public consultation was held between January and May 2020, to further explore and refine the scope of that ban – including a proposal to ban the use of ACM with unmodified polyethylene core and similar materials on all buildings in England. We are analysing feedback and will be publishing a response in due course.

Remediation

Since the Grenfell Tower fire, the Ministry of Housing, Communities and Local Government (MHCLG) and the Home Office (HO) have identified over 450 buildings with unsafe ACM cladding, and we have worked with local authorities and fire and rescue authorities to ensure that appropriate interim safety measures are in place, while these buildings undergo remediation.

In March this year the Government announced that it will provide £1 billion to fund the removal and replacement of unsafe non-ACM cladding systems. This is in addition to the £600 million which Government has made available for remediation of the highest risk ACM cladding. The prospectus for this fund was launched last month and sets out the buildings and non-ACM cladding systems that are eligible for funding and registration is now open for potential applicants, in advance of the full application process opening by the end of July 2020. More information on the Fund Prospectus can be found here: https://www.gov.uk/guidance/remediation-of-non-acm-buildings#prospectus---outlining-eligibility-for-the-fund.

This fund will meet the cost of remediating unsafe non-ACM cladding systems where building owners (or other entities legally responsible for making buildings safe) are unable to do so. Government are also providing additional, specialist project management capability to building owners or managing agents to speed up the development and implementation of building plans.

The Fire Protection Board

The Government has also established a Fire Protection Board, chaired by the National Fire Chiefs Council (NFCC), to provide greater assurance to central government of Fire and Rescue Service protection activity. The Board is leading a Building Risk Review Programme, supported by government funding to ensure that all high-rise residential buildings of 18m or above are inspected or reviewed by the end of 2021. We are also using a proportion of the additional £20m secured for fire and rescue services in the recent Budget to further support an uplift in protection capability.

Stay Put

At the end of last year, a joint HO and MHCLG steering group was set up to support a technical review of stay put. There are three strands to this work: an evidence review, assessing academic evidence on methods of evacuation; operational research to test evacuation strategies; and building design research. The first stage of this work has been commissioned and is underway whilst preliminary work is being carried out on the other strands.

Building safety

At the heart of the Government’s radical reforms to building safety is the new Building Safety Regulator, which we are establishing within the Health and Safety Executive. The Government set out plans in our response to the ‘Building a Safer Future’ consultation for the biggest change in building safety for a generation.

The new regulator will be responsible for implementing and enforcing a more stringent regulatory regime for higher risk buildings, as well as providing wider and stronger oversight of safety and performance across all buildings and increasing the competence of those working on building safety. This work complements the establishment of a new construction products regulatory role to strengthen national oversight and effectively enforce the new regulatory regime.

The Government will soon be publishing the draft Building Safety Bill for scrutiny before it is introduced in Parliament. This Bill will put in place this new and enhanced regulatory regimes for building safety and construction products, and ensure residents have a stronger voice.

In April, the Government published a workplan detailing the next steps for the wider review of Approved Document B, following the technical review that was started in December 2018. Research will be carried out in areas such as means of escape, compartmentation and toxicity. This work will build on the changes we have published in an update to Approved Document B last month, so that sprinklers and wayfinding signage will be provided in all new blocks of flats above 11 metres. The Government is also working with the NFCC on further tests of evacuation with a view to including guidance on provision of these systems in a later update to Approved Document B.

Fire Safety Bill

The Inquiry’s Phase 1 report also called for new duties on building owners and managers to share technical information with fire and rescue services and undertake regular inspections of flat entrance doors. It is our intention to take forward these recommendations for existing buildings under the Regulatory Reform (Fire Safety) Order 2005 underpinned by the changes being introduced through the Fire Safety Bill.

The Fire Safety Bill, which was introduced in March and received cross-party support, clarifies that the scope of the Fire Safety Order covers external walls (including cladding and balconies) and flat entrance doors in multi-occupied residential buildings. It provides a firm foundation upon which to bring forward secondary legislation to implement the recommendations that require further changes to the law. The Bill is a significant further step to ensure better identification and management of fire safety risks in such buildings.

It is important that the Government’s response to the Inquiry’s recommendations has the support of those with experience in these matters, and those most affected by them. To ensure their views inform our response, a public consultation will be issued soon setting out the Government’s proposed approach to the remaining recommendations that call for legislative change.

Fire and Rescue Services

Many of the recommendations within the Inquiry’s Phase 1 report were directed at non-Government organisations that are equally committed to the reforms. The report was clear that the London Fire Brigade (LFB) must learn and change to restore public confidence. Our request for regular progress reports from the LFB setting out how they are translating the recommendations into action are a key part of retaining focus and momentum on the need for change.

There remains much to do, but the HO is already seeing a commitment to revised policy and procedures backed up by the use of better equipment and technology to support high-rise fire fighting and fire fighting in London more broadly. The pandemic has created many challenges, but it has not affected the LFB’s commitment to implementing the Inquiry’s Phase 1 recommendations.

It is important that the lessons from Grenfell are learned beyond London. This is why the NFCC is working to ensure that the Phase 1 recommendations are implemented across all fire and rescue services. The HO is working closely with the NFCC on an improvement plan to help it drive real change across the sector.

In the three years since the Grenfell Tower fire, the Government has remained steadfast in its commitment to driving forward both cultural and legislative change so that no such tragedy can ever be allowed to happen again. Through implementation of the reforms highlighted in this statement, and wider work of Government and our stakeholders, we will move from the conditions that allowed a tragedy like the fire at Grenfell Tower to occur almost three years ago, to a system which ensures developers and building owners demonstrate greater responsibility for the safety of residents and which allows local authorities and fire and rescue authorities to enforce this. The Government is firmly committed to ensuring all residents are safe in their homes, now and in the future.

Original parliamentary record

Grenfell Tower Inquiry: Public Appointments

Written Question House of Commons
John Healey · Labour Answering body: Cabinet Office
Parliamentary excerpt

To ask the Minister for the Cabinet Office, pursuant to the Answer of 10 March 2020 to Question 25623 on Grenfell Tower Inquiry: Public Appointments, if he will place in the Library a copy of the contract entered into with the search company appointed to recruit a replacement panel member.

Government answer

Answering body: Cabinet Office

As part of the Government transparency agenda, it is a legal requirement for central Government Departments to publish all awarded contracts over £10,000 in value on the Contracts Finder website. Once a contract for this recruitment has been finalised and signed it will be published in the usual way.

Original parliamentary record

Grenfell Tower Inquiry: Public Appointments

Written Question House of Commons
John Healey · Labour Answering body: Cabinet Office
Parliamentary excerpt

To ask the Minister for the Cabinet Office, pursuant to the Answer of 10 March 2020 to Question 25623 on Grenfell Tower Inquiry: Public Appointments, which search company has been engaged to identify a shortlist of candidates; and by what date that compan

Government answer

Answering body: Cabinet Office

Further announcements will be made in the usual way.

Original parliamentary record

Grenfell Tower Inquiry: Public Appointments

Written Question House of Commons
John Healey · Labour Answering body: Cabinet Office
Parliamentary excerpt

To ask the Minister for the Cabinet Office, pursuant to the Answer of 10 March 2020 to Question 25623, if he has set a deadline for a replacement panel member to be appointed.

Government answer

Answering body: Cabinet Office

Further announcements will be made in the usual way.

Original parliamentary record

Grenfell Tower Inquiry: Public Appointments

Written Question House of Commons
John Healey · Labour Answering body: Cabinet Office
Parliamentary excerpt

To ask the Minister for the Cabinet Office, when a new panel member will be appointed to the Grenfell Tower inquiry; and what discussions he has with people affected by the Grenfell Tower fire on that appointment.

Government answer

Answering body: Cabinet Office

In February, the Prime Minister, as Sponsor Minister for the Grenfell Tower Inquiry, wrote to the Inquiry Chair to confirm his intention to appoint a replacement panel member. He also confirmed that Cabinet Office officials would engage a search company to identify a shortlist of candidates.

As soon as a suitable new panel member has been identified, the Prime Minister will write to the Inquiry Chair to seek his consent to the appointment as required by the Inquiries Act. The successful candidate will be announced once the process has been completed so they start work as soon as possible.

Original parliamentary record

Grenfell Tower Inquiry

Written Question House of Commons
John Healey · Labour Answering body: Home Office
Parliamentary excerpt

To ask the Secretary of State for the Home Department, with reference to the Grenfell Tower Inquiry phase 1 report, which Department is responsible for implementing the recommendations in that report; what the implementation status is of each such recommendation; and what the planned timescale is for implementing each of those recommendations.

Government answer

Answering body: Home Office

The Home Office is working collaboratively with the Ministry of Housing, Communities and Local Government, the Fire and Rescue Sector and all relevant stakeholders to deliver Grenfell Tower Inquiry phase 1 recommendations with quality, pace and ambition.

The Government published an update on delivery on 21 January and continues to make progress. As announced in the Queen’s Speech, we will shortly introduce a Fire Safety Bill, a necessary first step towards implementation of the Inquiry’s recommendations

Original parliamentary record

Boris Johnson: Grenfell Tower Inquiry

Written Question House of Commons
Steve Reed · Labour Answering body: Cabinet Office
Parliamentary excerpt

To ask the Minister for the Cabinet Office, whether he has submitted a witness statement to the Grenfell Tower Inquiry in Module Five in his capacity as a previous (a) Chair of the London Fire and Emergency Planning Authority and (b) Mayor of London.

Government answer

Answering body: Cabinet Office

The Inquiries Act 2005 empowers the Chair of an Inquiry to require the production of evidence, including from witnesses. The Prime Minister has received no requests for a witness statement from the Chair of the Grenfell Tower Inquiry. The London Fire Commissioner (which replaced LFEPA in 2017) is a core participant in the Inquiry.

Original parliamentary record

Buildings: Insulation

Written Question House of Commons
Steve Reed · Labour Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 6 February 2020 to Question 11599 on Buildings: Insulation, whether the Government has plans to mandate building owners to proactively share information on cladding; and what discussions he has had with the Home Secretary on including that step in the forthcoming Bill on fire safety.

Government answer

Answering body: Ministry of Housing, Communities and Local Government

The Home Office will bring forward legislation shortly to put beyond doubt that building owners and managers of all multi-occupied residential buildings must assess the risks from cladding and front doors to individual flats under the Regulatory Reform (Fire Safety) Order 2005. This legislation will:

require building owners to review their fire risk assessments to comprehensively cover all common parts of these buildings.

affirm that fire and rescue services can take appropriate enforcement action, in particular supporting the remediation of buildings with unsafe cladding in high rise buildings

provide the firm foundation required for taking forward recommendations from the Grenfell Tower Inquiry Phase One report (accepted in principle by the Government in October 2019), which called for new legal duties on building owners for high-rise residential buildings around inspection and information sharing with Fire and Rescue Authorities. A consultation on Home Office proposals is due to be issued in the spring.

Additionally, the forthcoming Building Safety Bill will put a requirement on dutyholders to ensure accurate and up-to-date building safety information is available and accessible to those who need it. A Mandatory Occurrence Reporting system will be established by the Building Safety Regulator, and dutyholders will be required to report any structural safety or fire safety related event which is perceived by them to represent a significant risk to life, in buildings within the scope of the new regime.

Original parliamentary record

High Rise Flats: Fire Prevention

Written Question House of Commons
Mr Stephen Morgan · Labour Answering body: Home Office
Parliamentary excerpt

To ask the Secretary of State for the Home Department, whether her Department has received representations on the Grenfell Tower Inquiry's consideration of changes in the level of fire safety regulation.

Government answer

Answering body: Home Office

A public consultation on the implementation of the Grenfell Tower Inquiry Phase 1 Report recommendations which require a change in law will be issued shortly. We have had early engagement with a range of stakeholders including the National Fire Chiefs Council, the Local Government Association, the Fire Industry Association, the Early Adopters group led by the Ministry of Housing, Community and Local Government, the Devolved Administrations and a number of other government departments.

The public consultation will give all those affected, including the Grenfell community, individuals, residents’ groups, building owners/managers and representatives from the fire safety industry, the opportunity to make their voices heard.

Original parliamentary record

Public Appointments: Standards

Written Question House of Commons
John Healey · Labour Answering body: Cabinet Office
Parliamentary excerpt

To ask the Minister for the Cabinet Office, pursuant to the Answer of 3 February 2020 to Question 8952 on Public Appointments: Standards, what assessment he has made of the adequacy of the due diligence process for appointments to the panels of statutory public inquiries following the resignation of Benita Mehra from her role as a panel member on the Grenfell Tower Inquiry.

Government answer

Answering body: Cabinet Office

Due diligence and consideration of conflicts of interest are important parts of any appointment process. The Inquiries Act 2005 sets out the suitability and impartiality requirements of inquiry panel appointments. Appointments to statutory public inquiries are made in accordance with the Act.

Original parliamentary record

High Rise Flats: Fires

Written Question House of Commons
Neil Coyle · Labour Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

To ask the Secretary of State for Housing, Communities and Local Government, with reference to the Grenfell Tower Inquiry Phase 1 report, if he will bring forward legislative proposals to ensure owners and managers of high-rise residential buildings introduce measures to support residents whose ability to self-evacuate may be compromised.

Government answer

Answering body: Ministry of Housing, Communities and Local Government

The Home Office will introduce a Fire Safety Bill in early 2020 which will put beyond doubt that owners or managers of multi-occupied residential buildings need to fully consider and mitigate the risks of external wall systems and front doors to individual flats.

The Fire Safety Bill will create a firm foundation to enable the Government to lay regulations to deliver the legislative recommendations from the Grenfell Tower Inquiry Phase 1 report, including in relation to personal evacuation plans for residents whose ability to evacuate may be compromised. A consultation on the Grenfell Tower Phase 1 legislative recommendations is planned for spring 2020.

In addition, the Ministry of Housing, Communities and Local Government has committed to bringing forward a Building Safety Bill. In our consultation, Building a Safer Future: proposals for reform of the building safety regulatory system, we set out proposals to create an enhanced safety framework for high-rise residential buildings. This included proposals for residents of buildings in scope of this new regime to receive key safety information about their building, which would include details about how to notify their ‘building safety manager’ if their ability to evacuate may be compromised. We will publish the response to our consultation shortly and will introduce legislation at the earliest opportunity.

Original parliamentary record

Public Appointments: Standards

Written Question House of Commons
John Healey · Labour Answering body: Cabinet Office
Parliamentary excerpt

To ask the Minister for the Cabinet Office, what assessment he has made of the adequacy of the due diligence process for public appointments following the resignation of Benita Mehra from her role as a panel member on the Grenfell Tower Inquiry.

Government answer

Answering body: Cabinet Office

Ms Mehra's appointment was not a public appointment. She was appointed to the panel of a statutory public inquiry in line with the Inquiries Act 2005.

Original parliamentary record

Buildings: Insulation

Written Question House of Commons
Steve Reed · Labour Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

To ask the Secretary of State for Housing, Communities and Local Government, what assessment he has made of the implications for his Department's policy on the applicability to cladding of paragraph 12.7 of the Approved Fire Regulations of the view expres

Government answer

Answering body: Ministry of Housing, Communities and Local Government

The steps which the Department took in relation to the guidance in Approved Document B are matters that will be looked at in the public inquiry into the Grenfell Tower fire.

Original parliamentary record

High Rise Flats: Fire Prevention

Written Question House of Lords
Lord Taylor of Warwick · Non-affiliated Answering body: Home Office
Parliamentary excerpt

To ask Her Majesty's Government, following the report of the Public Inquiry into the fire at Grenfell Tower on 14 June 2017 Grenfell Tower Inquiry: Phase 1 Report, published on 30 October, when they plan to introduce new fire safety legislation.

Government answer

Answering body: Home Office

The Government accepts, in principle, all the recommendations made of central Government in Grenfell Tower Public Inquiry’s Phase One report and will work at pace to take these forward. This may include bringing forward legislation ahead of the Bill on building safety standards announced in the Queen’s Speech if that would mean the Inquiry’s recommendations can be implemented sooner.

We are currently analysing responses to our Call for Evidence on the Regulatory Reform (Fire Safety) Order 2005 and intend to publish a formal response after the General Election.

Original parliamentary record

The Grenfell Tower Inquiry: Publication of its Phase 1 Report

Written Ministerial Statement House of Commons
Boris Johnson · Conservative Answering body: Prime Minister
Parliamentary excerpt

This morning, Sir Martin Moore-Bick has published the phase 1 report of the independent Grenfell Tower Inquiry. A copy of the report has been laid before each House of Parliament. This is a difficult day for all those who lost their loved ones, homes and possessions in that unimaginable tragedy, and found their lives devastated. Our first thoughts should be with them.The report is a very substantial document, which includes a detailed description of the events of the night of 14 June 2017, as...

Recorded statement

Answering body: Prime Minister

This morning, Sir Martin Moore-Bick has published the phase 1 report of the independent Grenfell Tower Inquiry. A copy of the report has been laid before each House of Parliament. This is a difficult day for all those who lost their loved ones, homes and possessions in that unimaginable tragedy, and found their lives devastated. Our first thoughts should be with them.

The report is a very substantial document, which includes a detailed description of the events of the night of 14 June 2017, as well as the Chair’s findings about the nature of the building, the origins of the fire, it’s subsequent development, the response of the London Fire Brigade and the steps taken by the other emergency services. It also contains a number of recommendations that my Government will consider with the utmost urgency. The bereaved, survivors and local residents have waited a long time for the Inquiry’s report, and it is right that the report should be debated in parliament on the day of its publication. But given the substantial nature of the report, and the limited time that parliamentarians have had to read the text, I am committed to holding a further debate at the earliest opportunity once Members have had an opportunity to properly scrutinise its contents. I hope that the bereaved and survivors can draw at least some solace from the rigorous, detailed nature of Sir Martin’s report.

Original parliamentary record