Public inquiry · Parliamentary scrutiny

Parliamentary activity

Grenfell Tower Inquiry. Read indexed debates, questions, statements and early day motions, with links to the original parliamentary records.

202 indexed mentions for this inquiry Earliest recorded mention: 21 June 2017

Parliamentary mentions

6 matching mentions · newest first

Doors: Fire Prevention

Written Question House of Commons
David Simmonds · Conservative Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

To ask the Secretary of State for Housing, Communities and Local Government, with reference to the Written Statement of 2 September 2024 on Building Safety, HCWS62, what the evidential basis is for the proposition that the European standard (BS EN 13501) is more rigorous and robust than the British fire door testing standard (BS 476-22).

Government answer

Answering body: Ministry of Housing, Communities and Local Government

The withdrawal of National Classes fire testing standards (BS 476) from Approved Document B in favour of the European Standard (BS EN 13501) aimed to enhance fire protection by simplifying compliance routes within the guidance. This change makes it easier and clearer to ensure products meet required standards and enabling simpler performance comparison.

The suitability of BS 476 and the transition to the EN standard was also scrutinised during the Grenfell Tower Inquiry. The EN suite of standards is constantly reviewed, periodically updated, and does not rely on withdrawn standards and is therefore seen as more suitable in the long term. The consultation response published alongside the Written Statement on 2 September 2024 shows a majority of respondents were in support of moving to the European Standard.

The Building Safety Regulator will keep these standards under review as part of their continuous review of Approved Document B, in line with their duty under the Building Safety Act to keep the safety and standard of buildings under review in England.

Original parliamentary record

Doors: Fire Prevention

Written Question House of Commons
David Simmonds · Conservative Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

To ask the Secretary of State for Housing, Communities and Local Government, what assessment she has made of the potential impact of the proposed transition period for moving from the BS 476-22 national fire door safety testing standard to the EN1634-1 standard on (a) the productivity of and (b) costs to timber fire door manufacturers.

Government answer

Answering body: Ministry of Housing, Communities and Local Government

On 2 September 2024, the Government announced the withdrawal of National Classes fire testing standards from Approved Document B, ending the dual classification system in favour of the European Standard (BS EN 13501). This change aimed to enhance fire protection by simplifying compliance routes within Approved Document B (ADB) and followed scrutiny during the Grenfell Tower Inquiry where the suitability of BS 476 was questioned.

The Government recognises the potential economic impact that could result from this change. The overall impact and associated benefits were carefully evaluated to inform the policy decision and are set out in the Impact Assessment that accompanied the policy announcement.

Market analysis and sector engagement showed limited impact on developers for the reaction to fire classification. Changes took effect on 2nd March 2025, with a six-month transition period provided for fire reaction.

We identified a larger impact on sectors involved in bespoke wooden fire doors, cavity barriers, smoke vents, and roofs due to re-testing requirements for the fire resistance classification. Concerns were also raised about testing site capacity. An extended transition period of 5 years was developed through discussions with the sector allowing manufacturers time to retest their products ahead of compliance with BS EN 13501 coming into force on 2nd September 2029.

We and the Building Safety Regulator will continue to support industry to develop new standards and testing capacity to minimise disruption to supply chains through the transitional period.

The Building Safety Regulator will keep these standards under review as part of their continuous review of Approved Document B, in line with their duty under the Building Safety Act to keep the safety and standard of buildings under review in England.

Original parliamentary record

Doors: Fire Prevention

Written Question House of Commons
David Simmonds · Conservative Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

To ask the Secretary of State for Housing, Communities and Local Government, whether her Department has made an estimate of the testing site capacity required to carry-out fire door tests for the new European Standard (EN1634-1) classification within the proposed transition period.

Government answer

Answering body: Ministry of Housing, Communities and Local Government

On 2 September 2024, the Government announced the withdrawal of National Classes fire testing standards from Approved Document B, ending the dual classification system in favour of the European Standard (BS EN 13501). This change aimed to enhance fire protection by simplifying compliance routes within Approved Document B (ADB) and followed scrutiny during the Grenfell Tower Inquiry where the suitability of BS 476 was questioned.

The Government recognises the potential economic impact that could result from this change. The overall impact and associated benefits were carefully evaluated to inform the policy decision and are set out in the Impact Assessment that accompanied the policy announcement.

Market analysis and sector engagement showed limited impact on developers for the reaction to fire classification. Changes took effect on 2nd March 2025, with a six-month transition period provided for fire reaction.

We identified a larger impact on sectors involved in bespoke wooden fire doors, cavity barriers, smoke vents, and roofs due to re-testing requirements for the fire resistance classification. Concerns were also raised about testing site capacity. An extended transition period of 5 years was developed through discussions with the sector allowing manufacturers time to retest their products ahead of compliance with BS EN 13501 coming into force on 2nd September 2029.

We and the Building Safety Regulator will continue to support industry to develop new standards and testing capacity to minimise disruption to supply chains through the transitional period.

The Building Safety Regulator will keep these standards under review as part of their continuous review of Approved Document B, in line with their duty under the Building Safety Act to keep the safety and standard of buildings under review in England.

Original parliamentary record

Doors: Fire Prevention

Written Question House of Commons
David Simmonds · Conservative Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

To ask the Secretary of State for Housing, Communities and Local Government, whether her Department plans to pause the proposed move from the British fire door safety testing standard (BS 476-22) to the European Standard (EN 1634-1) until the current review of the European Standard has been completed.

Government answer

Answering body: Ministry of Housing, Communities and Local Government

On 2 September 2024, the Government announced the withdrawal of National Classes fire testing standards from Approved Document B, ending the dual classification system in favour of the European Standard (BS EN 13501). This change aimed to enhance fire protection by simplifying compliance routes within Approved Document B (ADB) and followed scrutiny during the Grenfell Tower Inquiry where the suitability of BS 476 was questioned.

The Government recognises the potential economic impact that could result from this change. The overall impact and associated benefits were carefully evaluated to inform the policy decision and are set out in the Impact Assessment that accompanied the policy announcement.

Market analysis and sector engagement showed limited impact on developers for the reaction to fire classification. Changes took effect on 2nd March 2025, with a six-month transition period provided for fire reaction.

We identified a larger impact on sectors involved in bespoke wooden fire doors, cavity barriers, smoke vents, and roofs due to re-testing requirements for the fire resistance classification. Concerns were also raised about testing site capacity. An extended transition period of 5 years was developed through discussions with the sector allowing manufacturers time to retest their products ahead of compliance with BS EN 13501 coming into force on 2nd September 2029.

We and the Building Safety Regulator will continue to support industry to develop new standards and testing capacity to minimise disruption to supply chains through the transitional period.

The Building Safety Regulator will keep these standards under review as part of their continuous review of Approved Document B, in line with their duty under the Building Safety Act to keep the safety and standard of buildings under review in England.

Original parliamentary record

Doors: Fire Prevention

Written Question House of Commons
David Simmonds · Conservative Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

To ask the Secretary of State for Housing, Communities and Local Government, what the evidential basis is for proposals to remove the national BS 476-22 classification for fire door resistance from Approved Document B.

Government answer

Answering body: Ministry of Housing, Communities and Local Government

On 2 September 2024, the Government announced the withdrawal of National Classes fire testing standards from Approved Document B, ending the dual classification system in favour of the European Standard (BS EN 13501). This change aimed to enhance fire protection by simplifying compliance routes within Approved Document B (ADB) and followed scrutiny during the Grenfell Tower Inquiry where the suitability of BS 476 was questioned.

The Government recognises the potential economic impact that could result from this change. The overall impact and associated benefits were carefully evaluated to inform the policy decision and are set out in the Impact Assessment that accompanied the policy announcement.

Market analysis and sector engagement showed limited impact on developers for the reaction to fire classification. Changes took effect on 2nd March 2025, with a six-month transition period provided for fire reaction.

We identified a larger impact on sectors involved in bespoke wooden fire doors, cavity barriers, smoke vents, and roofs due to re-testing requirements for the fire resistance classification. Concerns were also raised about testing site capacity. An extended transition period of 5 years was developed through discussions with the sector allowing manufacturers time to retest their products ahead of compliance with BS EN 13501 coming into force on 2nd September 2029.

We and the Building Safety Regulator will continue to support industry to develop new standards and testing capacity to minimise disruption to supply chains through the transitional period.

The Building Safety Regulator will keep these standards under review as part of their continuous review of Approved Document B, in line with their duty under the Building Safety Act to keep the safety and standard of buildings under review in England.

Original parliamentary record

Grenfell Tower Inquiry

Written Question House of Commons
David Simmonds · Conservative Answering body: Ministry of Housing, Communities and Local Government
Parliamentary excerpt

To ask the Secretary of State for Housing, Communities and Local Government, what her planned timetable is for responding to the policy paper entitled Publication of the Grenfell Tower Inquiry phase 2 report, published on 4 September 2024.

Government answer

Answering body: Ministry of Housing, Communities and Local Government

We are considering the recommendations set out in the Grenfell Inquiry report. The Prime Minister has committed to respond in full to the Inquiry’s recommendations within six months.

Original parliamentary record