15

GCAP must break the mould of previous multilateral defence programme failures.

Conclusion
Whilst progress to date has been positive, previous multilateral defence programmes have frequently seen costs spiral and delays pile up and GCAP will have to break the mould if it is to achieve its ambitious target date. Decisions made at this early stage around partnerships, delivery structures and workshare by both Government and industry will be key to ensuring the aircraft arrives on time and to budget; and the importance of recruiting and retaining a suitably skilled workforce cannot be understated. The recommendations in this report are intended to help ensure that GCAP’s potential is fully realised. We will continue to provide robust scrutiny of the programme as it proceeds. (Conclusion, Paragraph 94) 32
Government Response

A response document is linked to this report, dated 21 March 2025. Response attribution to this conclusion has not been verified. Read the response document ↗