First Report - The New Hospital Programme
Public Accounts Committee
HC 77
Published 17 November 2023
Conclusions (1)
10
Conclusion
Not Addressed
After the evidence session, DHSC provided us with its current detailed schedule showing the approval and construction stages for each scheme to be completed by 2030. DHSC told us that this would be subject to detailed re-planning which is underway and asked us not to publish the information on the …
Government Response Summary
The government provides a generic statement about its commitment to rational decisions and balancing information protection, but does not address the committee's specific concerns about the feasibility of the construction schedule or contractor capacity.