Select committee: Public Accounts Committee
Conclusion 18
17th Report - The Remediation of Dangerous Cladding
Published 21 Mar 2025
Addressed to HM Treasury
Public Accounts Committee The Remediation of Dangerous Cladding All items in this report Report on parliament.uk ↗ Inquiry on parliament.uk ↗
Conclusion (the committee's words)
The National Fire Chiefs Council (NFCC) told us that the PAS 9980 standard for assessing the fire safety risk of external walls relied on specialist knowledge of building construction, fire engineering principles and material performance. The NFCC warned that there was limited availability of qualified professionals, and that its members were concerned that current PAS 9980 assessments were not meeting the intended standard. We also heard concerns from End Our Cladding Scandal and the NFCC about the inconsistent quality of fire risk appraisals and different assessors drawing different conclusions about what remediation work was required. The NFCC also told us that some PAS 9980 assessments were unjustifiably supporting the retention of combustible materials.29
From: Public Accounts Committee, 17th Report - The Remediation of Dangerous Cladding (HC 362), 21 March 2025
Government response
Latest Treasury Minutes progress report to the Committee of Public Accounts on the Seventeenth Report of Session 2024-26
The government responded to the whole report on 4 June 2026.
Treasury minutes: Government response to the Committee of Public Accounts on the Seventeenth report from Session 2024-25
Published 16 May 2025.
Summary written by Accountability Index from the government's response. It is not the government's own words.The government agrees with most of the Committee's recommendations on the remediation of dangerous cladding, with target dates between summer and December 2025, but disagrees with the recommendation on construction manufacturers paying a share of remediation costs.
- On the Remediation Acceleration Plan, the government agrees to update the Committee in Autumn 2025. It says it "has not seen significant evidence that non-cladding defects are slowing down remediation" but is committed to removing blockers.
- On construction manufacturers paying a share of remediation costs, the government disagrees. It says it is consulting on redress routes in the Construction Products Reform Green Paper and that leaseholders and tenants are protected from the cost of cladding remediation.
- The government will publish latest building number estimates "by the summer", but the timing of cost and completion date estimates "will depend on the outcome of the forthcoming Spending Review".
- On insurance, the government agrees and will share an update on progress by the end of 2025. It is gathering data on premiums and is considering whether government "might support industry to reduce fire related liabilities".