Select committee: Public Accounts Committee

Recommendation 14

17th Report - The Remediation of Dangerous Cladding Published 21 Mar 2025 Addressed to HM Treasury
Recommendation (the committee's words)
We asked MHCLG about what it was doing to support residents with non– cladding defects. MHCLG told us that it was developing a new standard with the British Standards Institute to give the sector more certainty over what work needed to be done to address non–cladding issues. It told us that owner-occupiers were protected from the costs of non-cladding defects, but that freeholders may have to meet them.20 Following the evidence session, EOCS wrote to us and reiterated situations where leaseholders were not protected.21 In written evidence, EOCS told us that non–cladding defects such as internal compartmentation, fire-stopping, fire doors or structural defects were defined as “life-critical” under the developer remediation contract and that costs to remediate them would be met by the developer. However, it told us that life-critical non-cladding defects were not within scope for buildings remediated through the government funded programmes, noting that the developer contract covered only 15–20% of all estimated buildings to be remediated.22 As the NAO’s report set out, where problems fall outside the scope of government programmes, costs may be passed on to leaseholders, who may be unable to afford them. The NAO’s report noted that the amount that could be charged to leaseholders was 17 Qq 1, 2 18 RDC0099, Written evidence submitted by the National Fire Chiefs Council, 4 February 2025 19 RDC0003, Written evidence submitted by The Property Institute, 4 February 2025 20 Q 46 21 Letter from End Our Cladding Scandal to Chair, Committee of Public Accounts, 17 February 2025 22 Q 1; RDC0145, Written evidence submitted by End Our Cladding Scandal, 4 February 2025 13 normally capped at £15,000 within Greater London and £10,000 elsewhere. EOCS told us in its letter that such costs were “life-changing” for most ordinary people, and they would not consider themselves “protected.” 23

From: Public Accounts Committee, 17th Report - The Remediation of Dangerous Cladding (HC 362), 21 March 2025

Government response

Latest Treasury Minutes progress report to the Committee of Public Accounts on the Seventeenth Report of Session 2024-26

The government responded to the whole report on 4 June 2026.

Read the government's response ↗ Report an error

Treasury minutes: Government response to the Committee of Public Accounts on the Seventeenth report from Session 2024-25

Published 16 May 2025.

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government agrees with most of the Committee's recommendations on the remediation of dangerous cladding, with target dates between summer and December 2025, but disagrees with the recommendation on construction manufacturers paying a share of remediation costs.

  • On the Remediation Acceleration Plan, the government agrees to update the Committee in Autumn 2025. It says it "has not seen significant evidence that non-cladding defects are slowing down remediation" but is committed to removing blockers.
  • On construction manufacturers paying a share of remediation costs, the government disagrees. It says it is consulting on redress routes in the Construction Products Reform Green Paper and that leaseholders and tenants are protected from the cost of cladding remediation.
  • The government will publish latest building number estimates "by the summer", but the timing of cost and completion date estimates "will depend on the outcome of the forthcoming Spending Review".
  • On insurance, the government agrees and will share an update on progress by the end of 2025. It is gathering data on premiums and is considering whether government "might support industry to reduce fire related liabilities".

Read the government's response ↗ Report an error