Select committee: Public Accounts Committee

Recommendation 12

17th Report - The Remediation of Dangerous Cladding Published 21 Mar 2025 Addressed to HM Treasury
Recommendation (the committee's words)
End Our Cladding Scandal (EOCS) told us it was not confident that MHCLG’s Plan would deliver for residents. It explained that too many barriers and issues remained, that MHCLG’s 2029 target was still five long years away and that it would only mean remediation was complete for some buildings–high rise buildings within the government’s grant programmes. EOCS said the target date, without an indication of when all buildings will be made safe, was essentially meaningless. It also told us that there were 13 Qq 30, 37; Ministry of Housing, Communities and Local Government, Joint plan to accelerate developer-led remediation and improve resident experience, Policy paper, published 2 December 2024 14 Qq 34, 36-37, 39; MHCLG Remediation Acceleration Plan 15 MHCLG Remediation Acceleration Plan 16 Qq 31, 40; MHCLG Remediation Acceleration Plan; C&AG’s Report para 2.2 12 still too many issues that were not being addressed by the Government’s programmes, including non–qualifying leaseholders, shared ownership and buildings under 11 metres and that non-cladding fire safety defects were holding up remediation.17

From: Public Accounts Committee, 17th Report - The Remediation of Dangerous Cladding (HC 362), 21 March 2025

Government response

Latest Treasury Minutes progress report to the Committee of Public Accounts on the Seventeenth Report of Session 2024-26

The government responded to the whole report on 4 June 2026.

Read the government's response ↗ Report an error

Treasury minutes: Government response to the Committee of Public Accounts on the Seventeenth report from Session 2024-25

Published 16 May 2025.

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government agrees with most of the Committee's recommendations on the remediation of dangerous cladding, with target dates between summer and December 2025, but disagrees with the recommendation on construction manufacturers paying a share of remediation costs.

  • On the Remediation Acceleration Plan, the government agrees to update the Committee in Autumn 2025. It says it "has not seen significant evidence that non-cladding defects are slowing down remediation" but is committed to removing blockers.
  • On construction manufacturers paying a share of remediation costs, the government disagrees. It says it is consulting on redress routes in the Construction Products Reform Green Paper and that leaseholders and tenants are protected from the cost of cladding remediation.
  • The government will publish latest building number estimates "by the summer", but the timing of cost and completion date estimates "will depend on the outcome of the forthcoming Spending Review".
  • On insurance, the government agrees and will share an update on progress by the end of 2025. It is gathering data on premiums and is considering whether government "might support industry to reduce fire related liabilities".

Read the government's response ↗ Report an error