Source · Select Committees · Public Accounts Committee

Recommendation 8

8 Accepted

MHCLG's cladding remediation targets considered too slow and incomplete, with works extending to 2035.

Recommendation
We asked MHCLG how its new plan would speed up the remediation process. MHCLG told us that its Ministers were committed to speeding up the pace of remediation. The Plan introduced a target that by the end of 2029 all buildings over 18 metres will have been remediated, and those between 11 and 18 metres will have been remediated, will have a date for completion, or owners will be liable for enforcement penalties. The target provides a means of assessing progress, as recommended by the NAO. However, 2029 is still 12 years on from the Grenfell fire and, as End Our Cladding Scandal pointed out, remediation works will only be completed for some buildings by then. MHCLG’s target did not set a date by which works on all 11–18 metre buildings should have started. The NAO found that MHCLG did not expect remediation works on some unsafe buildings to start until 2035.10
Government Response Summary
The government agrees and will publish an updated Remediation Acceleration Plan in Summer 2025, providing an update to the Committee in Autumn 2025, which will address policy and legislative changes, including creating a legal duty for 11m+ building owners to fix buildings within clear timescales.
Government Response Accepted
HM Government Accepted
1.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2025 1.2 The government is working to publish an update of the Remediation Acceleration Plan in Summer 2025; however, this is dependent on the outcome of the 2025 Spending Review. The update to the Committee will dovetail with this work, and therefore an update will be provided in Autumn 2025. 1.3 The update will address the (i) policy and legislative changes required to implement the Remediation Acceleration Plan and (iii) progress in identifying buildings with dangerous cladding. 1.4 For (ii), the government has not seen significant evidence that non-cladding defects are slowing down remediation. It is however committed to removing blockers to accelerate remediation and this will be included in the Autumn update. 1.5 For (iv), legislation exists that addresses the enforcement of internal and external fire safety defects. The government has however seen a need to strengthen legislation to make enforcement of cladding remediation more effective. It is therefore working towards creating a legal duty on those responsible for buildings at or above 11 metres to take the necessary steps to fix their buildings within clear timescales. An update will be included in the Autumn response.