Select committee: Public Accounts Committee

Conclusion 2

17th Report - The Remediation of Dangerous Cladding Published 21 Mar 2025 Addressed to HM Treasury
Conclusion (the committee's words)
Insufficient capacity and skills across regulators, local authorities and the construction sector risks undermining MHCLG’s acceleration plans. In 2020, the previous Committee warned that skills needed for remediation work would come under pressure as the scope of government’s programmes increased. With MHCLG now planning to accelerate remediation, there are risks that there will not be enough suitably qualified fire risk assessors to determine the scope of works, or trained cladders to undertake the work. This is likely to be exacerbated by a wider context of ambitious housebuilding targets and constrained construction sector capacity. Yet MHCLG appears complacent about the risks posed by this lack of capacity. Despite MHCLG’s assurances of additional funding and support for local authorities, local authorities may still lack the powers, capability or capacity to undertake the volume of necessary enforcement action. Where buildings are entering MHCLG’s portfolio, ongoing delays to building control approvals by the under–resourced Building Safety Regulator (BSR) could continue to hold up works on the highest risk buildings. We are alarmed to hear that BSR approvals are typically taking four to five times longer than the targeted 12 weeks. recommendation MHCLG should, by the end of July 2025, write to the Committee clearly setting out what action it is taking to help ensure there is sufficient capacity across the remediation system, and how it is assuring itself on progress.

From: Public Accounts Committee, 17th Report - The Remediation of Dangerous Cladding (HC 362), 21 March 2025

Government response

Latest Treasury Minutes progress report to the Committee of Public Accounts on the Seventeenth Report of Session 2024-26

The government responded to the whole report on 4 June 2026.

Read the government's response ↗ Report an error

Treasury minutes: Government response to the Committee of Public Accounts on the Seventeenth report from Session 2024-25

Published 16 May 2025.

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government agrees with most of the Committee's recommendations on the remediation of dangerous cladding, with target dates between summer and December 2025, but disagrees with the recommendation on construction manufacturers paying a share of remediation costs.

  • On the Remediation Acceleration Plan, the government agrees to update the Committee in Autumn 2025. It says it "has not seen significant evidence that non-cladding defects are slowing down remediation" but is committed to removing blockers.
  • On construction manufacturers paying a share of remediation costs, the government disagrees. It says it is consulting on redress routes in the Construction Products Reform Green Paper and that leaseholders and tenants are protected from the cost of cladding remediation.
  • The government will publish latest building number estimates "by the summer", but the timing of cost and completion date estimates "will depend on the outcome of the forthcoming Spending Review".
  • On insurance, the government agrees and will share an update on progress by the end of 2025. It is gathering data on premiums and is considering whether government "might support industry to reduce fire related liabilities".

Read the government's response ↗ Report an error