Source · Select Committees · Public Accounts Committee
Recommendation 19
19
There has been some improvement in the risk ratings applied to the programme.
Conclusion
There has been some improvement in the risk ratings applied to the programme. The most recent IPA review rated it as amber, having previously been amber-red following the reset. This was in response to improved governance and leadership in line with recommendations from the IPA and from an internal Department review.37 Despite these modest improvements the programme still rated its own scope risk as red as recently as August 2020 after one aspect of programme delivery slipped on its timeline, although it has since returned to amber.38 Coordination with related projects
Government Response
A response document is linked to this report, dated 31 August 2021. Response attribution to this conclusion has not been verified. Read the response document ↗