Conclusion 18

67th Report - NS&I’s transformation programme Published 13 Feb 2026 Addressed to HM Treasury
Conclusion (the committee's words)
NS&I had most of its operations contracted out when starting the Programme, and it had limited capability to deliver a digital transformation.46 NS&I told us it has found it difficult to recruit the additional skills and capability the Programme needs. It has made substantial use of consultants in the Programme, spending £43 million on advice.47 NS&I has found it particularly difficult to recruit technical roles, and is using secondments and temporary staff from other departments and the private sector, saying “it would not have made sense” to recruit into permanent roles.48 Since 2024, NS&I has added capability at senior levels, for example, by appointing a new commercial director, but it still relies on consultants to fill skills gaps.49

From: Public Accounts Committee, 67th Report - NS&I’s transformation programme (HC 1237), 13 February 2026

Government response

The government responded to the whole report on 7 April 2026 (deadline 13 April 2026).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government states that it "agrees with the Committee's recommendation" on each of the recommendations in the report, and sets target implementation dates between June and Autumn 2026.

  • On the integrated plan, the government agrees that NS&I should prepare a realistic plan. NS&I is developing costed options, which will form the basis of a revised Full Business Case in the second quarter of 2026-27, "subject to Treasury and Ministerial process timings".
  • NS&I will write to the Committee "within six months" setting out the integrated plan, including timelines and a revised estimated cost, and will provide a written update on its risk management framework "by June 2026".
  • On culture, a business-wide programme of cultural change activity will be developed, with an initial plan to go to the Board and the Treasury in early Summer 2026 for "rolling implementation over the coming 12-18 months".
  • The Treasury says it will evaluate NS&I's agreed plan through a full Treasury Approval Panel process and will write to the Committee in the Autumn on lessons learned from its oversight.