Select committee: Public Accounts Committee

Conclusion 11

67th Report - NS&I’s transformation programme Published 13 Feb 2026 Addressed to HM Treasury
Conclusion (the committee's words)
When we asked if decisions were being taken based on evidence, NS&I said that “there is always a chance that assumptions are incorrect”.26 The National Infrastructure and Service Transformation Authority had found that NS&I’s understanding of the alternative approaches had not been robust, and NS&I said its understanding had improved since the Programme started. However, it also sought to blame Atos’s financial difficulties, saying it had needed to spend time, energy and resources developing continuity plans instead of on the Programme.27 NS&I dismissed suggestions that it should have done more work at the start, saying “you can always do more analysis”, and appeared to blame suppliers for not bidding for Programme contracts.28 A good news culture can prevent lessons being learnt

From: Public Accounts Committee, 67th Report - NS&I’s transformation programme (HC 1237), 13 February 2026

Government response

The government responded to the whole report on 7 April 2026 (deadline 13 April 2026).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government states that it "agrees with the Committee's recommendation" on each of the recommendations in the report, and sets target implementation dates between June and Autumn 2026.

  • On the integrated plan, the government agrees that NS&I should prepare a realistic plan. NS&I is developing costed options, which will form the basis of a revised Full Business Case in the second quarter of 2026-27, "subject to Treasury and Ministerial process timings".
  • NS&I will write to the Committee "within six months" setting out the integrated plan, including timelines and a revised estimated cost, and will provide a written update on its risk management framework "by June 2026".
  • On culture, a business-wide programme of cultural change activity will be developed, with an initial plan to go to the Board and the Treasury in early Summer 2026 for "rolling implementation over the coming 12-18 months".
  • The Treasury says it will evaluate NS&I's agreed plan through a full Treasury Approval Panel process and will write to the Committee in the Autumn on lessons learned from its oversight.

Read the government's response ↗ Report an error