Twenty-First Report: Transforming electronic monitoring services Published 21 Oct 2022 Addressed to HM Treasury
Conclusion (the committee's words)
In early 2022, HMPPS decided to outsource this role again in its re-procurement and transition to the new service. The NAO outlined areas where HMPPS will need to be prepared to manage risks with this approach, including: • Parties having different interpretations of what the integrator role involves and where accountability sits if problems arise; • The integrator having no contractual oversight of the other supplier; and • The potential for real or perceived conflicts of interest, given that its field services supplier will be responsible for delivering substantial work while integrating others’ work.52

From: Public Accounts Committee, Twenty-First Report: Transforming electronic monitoring services (HC 34), 21 October 2022

Government response

The government responded to the whole report on 14 December 2022 (deadline 21 December 2022).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government states that it agrees with each of the Committee's six recommendations on the Ministry of Justice's electronic monitoring services, and gives target implementation dates for five of them.

  • On real-time police access to GPS data, the government agrees with the recommendation, but says police have advised that live access is not a current priority; it will "consider whether and how changes to the service can be made" should the police's view change.
  • On outdated technology, remediation work has moved from December 2022 to March 2023, and system improvements "by the end of January 2023" are intended to let the GPS system cope with rising volumes.
  • On evidence of impact, a benefits management strategy and realisation plan will be in place "By April 2023", and a formal evaluation strategy for electronic monitoring is being developed. The target implementation date is August 2023.
  • On oversight of the expansion programme, the agency commits to write to the Committee in August 2023, once new contracts have been awarded.