New Hospital Programme
Closed
What the inquiry looked at
“The New Hospital Programme was set up in 2020 to build 40 new hospitals in England by 2030. It has £3.7 billion in capital funding for this for up to March 2025, with more to be provided for the following five years. The Programme is also intended to transform how NHS healthcare infrastructure is built, including by standardising hospital design. The Committee found in July 2020 that NHS Trusts had a £6.5bn backlog of maintenance to restore their estates to an appropriate standard. This backlog has since increased to £10.2bn. Based on a National Audit Office report examining whether the Department of Health and Social Care (DHSC) and NHS England are managing the Programme in a way that is likely to achieve value for money, the Committee will question senior DHSC officials on subjects including: national programme management support for and challenges to local projects within the Programme progress compared with expectations the management of programme-level risks If you have evidence on these issues, please submit it here by 23:59 on Friday 25 August 2023. Please look at the requirements for written evidence submissions and note that the Committee cannot accept material as evidence that is published elsewhere.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The New Hospital Programme (NHP) was intended to be a landmark programme, addressing the escalating backlog of investment in hospital buildings by delivering 40 new hospitals in England by 2030. The programme has been marked by slower progress and higher costs than promised, a lack of transparency in scheme selection, and until a few months ago uncertainty about overall funding, scope and timetable. It is now clear that NHP will not deliver all 40 new hospitals by 2030 and is highly unlikely even to construct the 32 new hospitals (under its 2020 definition) that it is now aiming to complete.
The Department of Health and Social Care (DHSC) was aware in 2020 that there were seven NHS hospitals built entirely of reinforced autoclaved aerated concrete (RAAC)
which had become structurally unsound. Yet only two of these seven were selected for inclusion in the programme at that time. In May 2023, DHSC reset NHP and included the other five RAAC hospitals. In all seven, costly mitigation measures are required to keep services running until new structures can be built. The 2023 programme reset had the effect of delaying eight other hospitals, which DHSC now will not complete until after 2030, a major disappointment for people living in those communities.
An important feature of NHP is DHSC’s aspiration to develop new cheaper and faster approaches to hospital construction. This includes a new standardised hospital design called ‘Hospital 2.0’. Resourcing and design capacity issues have hampered the progress of Hospital 2.0 and development of the design and process is now running at least five months behind schedule. The delay to Hospital 2.0 has impacted the programme in two key ways. It has reduced the time available to pilot the new design in real-life scenarios, risking baking-in and replicating design and construction problems across England. The delay has also hindered meaningful engagement between NHP and the construction industry on the details of the design and the commercial pipeline of work.
There are big questions about the industry’s capacity and appetite to build the required number of hospitals in the new way and to a very tight timetable.
Most worryingly of all, the latest version of Hospital 2.0 is based on assumptions that appear very likely to produce hospitals that are too small. The NHP team is assuming future bed occupancy rates of 95% and reductions in length of patient stay that are unsupported by research it commissioned. The assumptions look particularly heroic in the context of the UK’s growing and ageing population, while there is as yet no social care plan in place to alleviate the increasing pressure on hospitals.
DHSC and NHS England have generally failed to build capacity within the NHP team. With 62% of NHP posts filled using consultancy services in February 2023, the programme has been over-reliant on consultants, creating risks of lack of continuity and capability at the heart of the programme as well as making it more expensive.
The Government indicated in March 2023 that the maximum capital funding available to deliver 32 new hospitals by 2030–31 as well as completing eight pre-existing schemes would be £22.2 billion (made up of the original funding up to 2024–25 of £3.7 billion plus an additional £18.5 billion from 2025–26 onwards). The Committee sees multiple affordability challenges which DHSC needs to grapple with, including the fact that changes to the assumptions underlying Hospital 2.0 to make the design fit for purpose will likely increase costs.
What the government said
The government responded on 8 March 2024. The deadline was 17 January 2024.
The government states that it agrees with most of the Committee's recommendations, disagrees with the recommendation to start construction of an early standardised-design scheme during 2024, and "notes" a recommendation addressed to another committee.
- On standardised design, the government disagrees with starting construction in 2024, saying "construction is unlikely to start in 2024" because starting before design maturity "ends up costing time and money". It intends to test Hospital 2.0 "at the earliest opportunity" within one of the RAAC schemes.
- On RAAC, the government agrees, but says publishing surveys in full "will not be possible" due to commercially sensitive information. It will keep the 2035 eradication commitment "under review" and "aim[s] to begin early works to prepare sites by the end of 2025" for the seven RAAC hospitals.
- On scheme selection records, the government agrees. It accepts "there was an omission in record keeping" in 2019 and says it will provide evidence on decision outcomes "as needed", balanced against protecting commercially sensitive information.
- On skills and consultancy, the government agrees and says the department "will write to the Committee by March 2024". It also considers a programme delivery partner approach "necessary".
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 20 July 2023 to its close on 8 March 2024. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 7 Sep 2023
- Report 17 Nov 2023
- Government response 8 Mar 2024
- Correspondence 2 letters
What it recommended 1 recommendation · 41 conclusions
2DHSC lacks proper records to justify Health Infrastructure Plan scheme selections.
3Revise DHSC's RAAC crisis management plans, expediting surveys and replacement hospital construction.
4Start construction by 2024 on an early scheme piloting standardised hospital design.
5Amend Hospital 2.0 design to prevent undersized hospitals and assess national capacity.
6Agree explicitly on funding for delayed hospital schemes and realistic programme costs.
7Develop strategy for attracting and retaining civil service skills for hospital construction.
8Safeguard planned capital investment from diversion to meet day-to-day spending needs.
1Committee took evidence on the New Hospital Programme from DHSC and NHS England.
9DHSC delayed in creating standardised hospital design and approval processes.
10DHSC's confidential hospital construction schedule indicates extensive simultaneous building by 2030.
11New Hospital Programme's cost and time saving estimates for standard design are very ambitious.
12NHP's Hospital 2.0 standard design development is significantly behind schedule, now expected May 2024.
13Insisting on unproven Hospital 2.0 designs for urgent RAAC hospital rebuilds by 2030 is questionable.
14DHSC remains reluctant to conduct rigorous real-life testing of the Hospital 2.0 design.
15Require the New Hospital Programme to conduct comprehensive live clinical testing of Hospital 2.0 designs.
16Hospital 2.0 Minimum Viable Product assumptions are unrealistic, risking undersized hospitals for future needs.
17NHS Providers warn Hospital 2.0's 95% bed occupancy assumption is unsustainable and unsafe.
18DHSC promises rigorous review of Minimum Viable Product assumptions, despite potential affordability issues.
19NHS England confirms single room wards require significant changes in staff mix and numbers.
20RAAC in hospitals causes severe disruption and clinical risks, impacting patient care.
21Initial New Hospital Programme excluded five known RAAC hospitals until 2023 reset.
22Government committed to remove RAAC by 2035 with time-limited funding allocation.
23More RAAC buildings likely, straining limited specialist engineering resources across government.
24Future funding for RAAC remediation beyond 2024-25 remains uncertain despite 2030 eradication goal.
25Trusts primarily responsible for RAAC risk management, despite some national technical support.
26Replacing seven high-cost RAAC hospitals by 2030 poses significant challenge and closure risk.
27New Hospital Programme expanded to 48 schemes, incorporating HIP and pre-existing projects.
28Lack of documentation for HIP scheme selection severely hindered transparency and NAO scrutiny.
29DHSC acknowledges "extremely disappointing" lack of records for past HIP scheme selection process.
30Government consistently lacks transparency and evidence in justifying scheme selection, fueling political bias concerns.
31Hospitals removed from the shortlist face critical infrastructure risks due to growing maintenance backlog.
32New Hospital Programme, initially \
33New Hospital Programme's early scheme forecast costs increased by 41%, risking significant overruns.
34New Hospital Programme's optimistic assumptions risk further cost overruns and insufficient funding for all schemes.
35New Hospital Programme faces significant commercial risks from construction capacity shortages and high inflation.
36Significant funding \
37New Hospital Programme aims to build national capability in hospital delivery, using consultants for specific expertise.
38New Hospital Programme heavily relies on consultants, consuming 79% of its day-to-day expenditure.
39DHSC's future plans contradict reducing consultant reliance, projecting £842 million spend by 2031.
40DHSC's neglect of long-term NHS sustainability led to a record maintenance backlog.
41Under-investment in NHS capital impedes productivity and compromises modern healthcare environment standards.
42New Hospital Programme expected to address approximately one-third of existing NHS maintenance backlog.
Evidence
Oral evidence sessions 1
- 7 Sep 2023New Hospitals Programme5 witnesses, listed belowparliament.uk ↗
Who gave evidence 5 witnesses
- Amanda PritchardChief Executive Officer, NHS England
- Julian KellyDeputy Chief Executive Officer & Chief Financial Officer, NHS England
- Natalie ForrestSenior Responsible Owner for the New Hospitals Programme, Department of Health and Social Care
- Professor Sir Stephen PowisNational Medical Director, NHS England
- Shona DunnSecond Permanent Secretary, Home Office
Correspondence 2 letters
- 26 Feb 2024Correspondence from Shona Dunn, Second Permanent Secretary, Department of Health and Social Care, re Reinforced Autoclave Aerated Concrete, dated 15 February 2024
- 16 Oct 2023Correspondence from Shona Dunn, Second Permanent Secretary, Department for Health and Social Care, re Public Accounts Committee New Hospital Programme Hearing – 7 September 2023, dated 26 September 2023