HS2 Euston
Closed
What the inquiry looked at
“The Committee will question Dame Bernadette Kelly, Permanent Secretary at the Department for Transport and Mark Thurston, Chief Executive of HS2 Ltd on progress with the design and development of a new HS2 station at Euston. Questions will include how the risks to value for money are being managed, integration with other developments including the redeveloped Network Rail station, and the overland developments on the site. This work builds on the Committee’s 2020 , 2021 and 2022 updates on the HS2 project. If you have new evidence specifically on the development of the London Euston terminal, please submit it here by 6pm on 9April 2023. Please have a look at the requirements for written evidence submissions and note the Committee cannot accept as evidence material that has been published elsewhere.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
Despite being eight years into planning the High Speed 2 station at Euston, the Department for Transport (the Department) still does not know what it is trying to achieve with the station and what sort of regeneration it will support. It is clear now that the £2.6 billion budget HS2 Ltd set for the project was completely unrealistic, even before the impacts of inflation are considered. The Department will now need to reset the project for a second time in order to find a design that is realistic, affordable and provides value for money.
The Department does not know what the additional costs and impacts will be from its decision to pause construction at the station for two years. Working alongside HS2 Ltd, it now has a big task to identify what these costs and impacts are, including the impact on the supply chain and on local residents. It is essential for the Department to collect this information both to help it and HS2 Ltd manage the additional costs effectively and also to better inform any decisions in the future on whether to pause major projects.
Disappointingly, HS2 Euston station is yet another example of the Department making the same mistakes and failing to learn lessons from its management of other major rail programmes. Parliament has also not had the full transparency it needed on the likelihood of cost increases at Euston, despite the improvements the Department and HS2 Ltd have made in reporting on progress.
What the government said
The government responded on 24 September 2023. The deadline was 7 September 2023.
The government agrees with the Committee's recommendations on setting an affordable Euston design, budget transparency, inflation and lessons learned, and disagrees with the recommendations on an interim report on pause costs and on the content of six-monthly HS2 reports.
- On design and budget, the government agrees, with a target implementation date of Summer 2025. The Euston Reset Programme aims to confirm an updated scheme which is "affordable and deliverable, by April 2025", and a new delivery-into-service date "will be provided in due course".
- The government disagrees with the recommendation for an interim report on the costs of the pause. It says it will write to the Committee on spend to date "once this information is available from HS2 Ltd and its suppliers".
- On inflation and contingency, the government agrees, with a target date of January 2024. DfT and HM Treasury "will report back to the Committee in six months" on managing future cost pressures, and the department will update the Committee in six months on the requirements for accessing government-held contingency.
- On six-monthly reports, the government agrees on explaining cost estimate maturity (target December 2023) but disagrees with the Committee's wider recommendation. Benefit-Cost Ratios "will not be included" in the reports, and it intends to update the price base "subject to agreement" with HM Treasury.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 15 February 2023 to its close on 24 September 2023. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 24 Apr 2023
- Report 7 Jul 2023
- Government response 24 Sep 2023
- Correspondence 15 May 2023
What it recommended 13 recommendations · 14 conclusions
2Ensure realistic and affordable Euston station budget and design before restarting construction.
3Produce interim report on Euston pause costs and supply chain impact within three months.
4Establish plan with Treasury for managing inflation and HS2 programme contingency.
5Provide clear explanations of HS2 Euston cost estimate maturity and risks in six-monthly updates
1Existing HS2 Euston report was late and lacked sufficient cost information
6Demonstrate embedded lessons from past rail projects and specific measures addressing Euston cost overruns
7Department exploring minimum and value-maximisation design options for HS2 Euston station
8Pause in HS2 Euston construction used to develop affordable, passenger-focused design
9Initial HS2 Euston station budget was a 'stretch target' and significantly underestimated costs
10HS2 Ltd identified significant efficiencies to meet affordable overall project costs
11HS2 Euston cost estimates increased to £4.8 billion, requiring substantial reductions for affordability
12Costs of pausing HS2 Euston construction remain unknown, with significant winding-up expenses expected
13Impact of HS2 Euston construction pause on the supply chain remains undetermined
14HS2 Ltd actively managing contract pauses but not receiving formal claims from contractors.
15Local communities impacted by HS2 pause, seeking transparency and input on interim solutions.
16Significant inflationary pressures led Department to pause HS2 and road building projects.
17Department discusses HS2 inflation management with Treasury, recognising mid-year cuts' poor value.
18Unclear purpose and drawdown mechanisms for HS2 Phase One's £4.3 billion contingency fund.
19Department's HS2 reports commenced, identifying an early £0.4 billion Euston cost pressure.
20Euston cost pressure consistently reported as £0.4 billion despite expected reductions from design changes.
21HS2 Euston's actual cost estimate of £4.8 billion greatly exceeded previously reported figures.
22HS2 Ltd's two-stage procurement process delays confident cost estimates for complex projects.
23Department delayed HS2 six-monthly report, providing limited new information to Parliament.
24Recurring departmental failures in budgeting, cost estimation, and integration across major rail programmes
25Department has not demonstrably embedded lessons learned into major rail programmes
26Department identifies recurring lessons from Euston for future complex station developments
27Advanced HS2 stations provide valuable data for later phases and integrated development
Evidence
Oral evidence sessions 1
- 24 Apr 2023HS2 Euston3 witnesses, listed belowparliament.uk ↗
Who gave evidence 3 witnesses
- Alan OverDirector General, Major Rail Projects Group, Senior Responsible Owner for High Speed 2 Programme, Department for Transport
- Dame Bernadette Kelly DCBPermanent Secretary, Department for Transport
- Mark ThurstonChief Executive, HS2 Ltd