DCMS recall (Broadband)

Status: Closed Opened: 21 Sep 2021 Closed: 7 Apr 2022 5 recommendations 22 conclusions 1 report

In January 2021 the Committee reported that problems with the rollout of superfast broadband across the UK meant that digital inequality risks compounding the economic inequality “harshly” exposed by the pandemic . In this inquiry the Committee will recall DCMS officials for an update on progress towards the Government’s revised timeline for rolling out broadband … Show more

Clear

Reports

1 report
Title HC No. Published Items Response
Thirty-Second Report - Delivering gigabitcapable broadband HC 743 19 Jan 2022 27 Responded

Recommendations & Conclusions

10 items
2 Recommendation Thirty-Second Report - Delivering gigab… Accepted

The Department has so far been overly reliant on the contributions of commercial suppliers in...

The Department has so far been overly reliant on the contributions of commercial suppliers in improving gigabit coverage. The Department is reliant on suppliers to deliver gigabit coverage to 80% of UK premises without subsidy. Between May and October 2021, national gigabit coverage increased from 40% to 57%. The Department … Read more

Government response AI summary
BDUK will report further details on the coverage achieved by its different interventions in its performance report in July 2022, and then in the annual report and accounts from 2023.
Read full response →
HM Treasury
3 Recommendation Thirty-Second Report - Delivering gigab… Accepted

We are not convinced by the Department’s assertion that it will meet its target delivery...

We are not convinced by the Department’s assertion that it will meet its target delivery of a minimum of 85% by 2025 despite having signed no new infrastructure subsidy contracts for Project Gigabit. The Department’s previous target proved to be unachievable. Despite revising the overall target, the Department’s target dates … Read more

Government response AI summary
The government agrees with the Committee’s recommendation and BDUK’s 2022-23 corporate plan will include a baseline trajectory for the progress required each year and will report progress against this baseline annually, beginning July 2022. The department will address this recommendation in its letter to the …
Read full response →
HM Treasury
4 Recommendation Thirty-Second Report - Delivering gigab… Accepted

We are disappointed that the Department has still not taken significant action to remove barriers...

We are disappointed that the Department has still not taken significant action to remove barriers to rolling out Project Gigabit. Despite our recommendation earlier this year, the Department has yet to secure the legislative and policy changes that industry deems necessary to address major barriers to delivering gigabit infrastructure at … Read more

Government response AI summary
The government agrees with the Committee’s recommendation and will provide a letter setting out progress on removing barriers to deployment and removing equipment from high-risk vendors, outlining specific actions already taken like introducing the Product Security and Telecommunications Infrastructure Bill and consulting on a proposed …
Read full response →
HM Treasury
5 Recommendation Thirty-Second Report - Delivering gigab… Accepted

The Department’s approach to rolling out gigabit risks perpetuating digital inequality across the UK.

The Department’s approach to rolling out gigabit risks perpetuating digital inequality across the UK. The Department contends that it is taking an “Outside- In” approach to gigabit infrastructure procurement. As part of this approach, the Department identifies areas which it does not expect it to be viable for commercial providers … Read more

Government response AI summary
BDUK will strengthen its quarterly reports with further information on progress in UK gigabit coverage, including regional and national progress, rural vs. urban areas, and businesses vs. residential premises, sourced from ThinkBroadband.com and Ofcom's Connected Nations reports.
Read full response →
HM Treasury
12 Conclusion Thirty-Second Report - Delivering gigab… Accepted

The Department told us that the reason it had yet to sign any new gigabit...

The Department told us that the reason it had yet to sign any new gigabit infrastructure contracts was largely that commercial operators hadaccelerated their plans for expanding gigabit coverage very rapidly. It explained that this has meant that it needed to re-plan on the basis that the private sector has … Read more

Government response AI summary
BDUK balances the need to be dynamic and responsive to the market’s plans while maintaining a minimum level of certainty. BDUK has implemented a process for surveying contract areas to understand suppliers’ commercial build plans. BDUK has streamlined its procurement process, while maintaining Public Contracting …
Read full response →
HM Treasury
14 Conclusion Thirty-Second Report - Delivering gigab… Accepted

In our January 2021 report we concluded that the Department had failed to make meaningful...

In our January 2021 report we concluded that the Department had failed to make meaningful progress in tackling barriers faced by operators in maximising gigabit connectivity. We noted that it had yet to secure the legislative and policy changes that industry deemed necessary for removing major barriers at pace and … Read more

Government response AI summary
The department has introduced the Product Security and Telecommunications Infrastructure Bill, worked with the DfT and industry to implement and trial further reforms to streetworks and permitting, published a statutory technical consultation on ‘new build’ home gigabit-capable connectivity, introduced changes to permitted development rights, and …
Read full response →
HM Treasury
16 Conclusion Thirty-Second Report - Delivering gigab… Accepted

The Department also held a technical consultation on the regulations needed to implement the Telecommunications...

The Department also held a technical consultation on the regulations needed to implement the Telecommunications Infrastructure (Leasehold Property) Act from June to August 2021. However, it has not yet published either the findings of the consultation or its response to these.48 Similarly, the Department is still analysing feedback on the … Read more

Government response AI summary
The department has introduced the Product Security and Telecommunications Infrastructure Bill, worked with the DfT and industry to implement and trial further reforms to streetworks and permitting, published a statutory technical consultation on ‘new build’ home gigabit-capable connectivity, introduced changes to permitted development rights, and …
Read full response →
HM Treasury
17 Conclusion Thirty-Second Report - Delivering gigab… Accepted

Stakeholders also suggested that there were areas where the Department’s approach to removing barriers to...

Stakeholders also suggested that there were areas where the Department’s approach to removing barriers to rolling out gigabit-capable infrastructure could be strengthened further.53 This was particularly the case regarding “wayleaves,” which are contractual agreements between landowners and telecommunications providers about the right to access property in order to install and … Read more

Government response AI summary
The department has introduced the Product Security and Telecommunications Infrastructure Bill, worked with the DfT and industry to implement and trial further reforms to streetworks and permitting, published a statutory technical consultation on ‘new build’ home gigabit-capable connectivity, introduced changes to permitted development rights, and …
Read full response →
HM Treasury
20 Conclusion Thirty-Second Report - Delivering gigab… Accepted

In our report in January 2021, we found that the Department was still developing its...

In our report in January 2021, we found that the Department was still developing its £5 billion programme to subsidise roll-out to the hardest to reach 20% of the UK’s 31 million premises and could not tell us when it intends to deliver major milestones, such as the letting of … Read more

Government response AI summary
BDUK's programme strategy and design of its interventions balances the need to be dynamic and responsive to the market’s plans while maintaining a minimum level of certainty and has implemented a robust process for surveying contract areas to understand suppliers’ commercial build plans. BDUK reviews …
Read full response →
HM Treasury
21 Conclusion Thirty-Second Report - Delivering gigab… Accepted

We asked the Department why it had not just pressed ahead with the areas that...

We asked the Department why it had not just pressed ahead with the areas that it already knows are commercially unviable in the long term. It pointed us to Cumbria which had recently “been procured” and said that Cambridgeshire was also in the same batch. However, these are a small … Read more

Government response AI summary
BDUK balances the need to be dynamic and responsive to the market’s plans while maintaining a minimum level of certainty. BDUK has implemented a process for surveying contract areas to understand suppliers’ commercial build plans. BDUK has streamlined its procurement process, while maintaining Public Contracting …
Read full response →
HM Treasury

Oral evidence sessions

1 session
Date Witnesses
4 Nov 2021 Imran Shafi · Department for Digital, Culture, Media and Sport, Paul Norris · Building Digital UK, Sarah Healey · Department for Digital, Culture, Media and Sport, Susannah Storey · Department for Digital, Culture, Media and Sport View ↗

Who gave evidence

4 witnesses
WitnessOrganisationSessions
Imran Shafi · Director for Digital Infrastructure Department for Digital, Culture, Media and Sport 1
Paul Norris · Chief Executive Building Digital UK 1
Sarah Healey · Permanent Secretary Department for Digital, Culture, Media and Sport 1
Susannah Storey · Director General for Digital and Media Department for Digital, Culture, Media and Sport 1

Correspondence

4 letters
DateDirectionTitle
7 Feb 2022 Correspondence from Sarah Healey, Permanent Secretary, Department for Digital, …
6 Dec 2021 Correspondence from the Department for Digital, Culture, Media and Sport relati…
6 Dec 2021 Correspondence to the Department for Digital, Culture, Media and Sport relating…
2 Nov 2021 Correspondence from Sarah Healey, Permanent Secretary, Department for Digital, …