Select committee: Welsh Affairs Committee
Conclusion 11
First Report - Grid Capacity in Wales
Published 21 Oct 2022
Paragraph 74
Addressed to Wales Office
Welsh Affairs Committee Grid capacity in Wales All items in this report Report on parliament.uk ↗ Inquiry on parliament.uk ↗
Conclusion (the committee's words)
Larger companies have a financial advantage linked to scale, whereas smaller energy projects are often reliant on the development of larger projects and the availability of spare capacity once these have been completed.
From: Welsh Affairs Committee, First Report - Grid Capacity in Wales (HC 218), paragraph 74, 21 October 2022
Government response
The government responded to the whole report on 24 January 2023 (deadline 21 December 2022).
Summary written by Accountability Index from the government's response. It is not the government's own words.The government welcomes the Committee's report and says it will continue work on strategic planning, regulatory approval, planning consents and streamlining connections, while declining some recommendations on working groups, legislation and Ofgem's duty.
- On Ofgem's primary duty, the government "does not consider an amendment to Ofgem's primary duty to be necessary", saying the duty to protect consumers' interests already includes reducing emissions in line with net zero.
- On community energy, it will not establish a working group "at this time", citing the existing Community Energy Contact Group, and has "no plans to bring forward legislative proposals, at this time".
- On connection costs, it notes that from April 2023 Ofgem will socialise a further proportion of network reinforcement costs for distribution connection customers, which "will reduce the upfront cost".
- On planning, it intends to publish a full NSIP Reform Action Plan and consultations "in due course", and says revised energy National Policy Statements will be published "soon".