Source · Select Committees · Environmental Audit Committee

First report - Building to net zero: costing carbon in construction

Environmental Audit Committee HC 103 Published 26 May 2022
Report Status
Government responded
Conclusions & Recommendations
48 items (29 recs)
Government Response
AI assessment · 48 of 48 classified
Accepted 14
Accepted in Part 3
Acknowledged 20
Deferred 8
Not Addressed 1
Rejected 2
Government response
Third Special Report - Building to net zero: costing carbon in construction: Government Response to the Committee’s First Report · published 30 Sep 2022
Read the government response ↗ Response on the Index
Filter by: Clear

Recommendations & Conclusions

1 item
35 Recommendation Not Addressed

We recommend that, in its response to this report, the Government should set out the...

Recommendation
We recommend that, in its response to this report, the Government should set out the number and proportion of public works construction projects for which whole- life carbon assessments have been undertaken pursuant to the provision in the 2020 Construction … Read more
Government Response Summary
The government states that the Construction Playbook sets out best practice guidance, including the use of whole life carbon assessments, but there are no plans to collect and publish information on the number of projects where an assessment has not been undertaken. However, they are exploring a set of industry recognised standards and guidance for WLC assessment.
View Details →