Select committee: Energy Security and Net Zero Committee

Recommendation 15

4th Report - The new National Policy Statement for nuclear energy generation Published 24 Oct 2025 Addressed to Department for Energy Security and Net Zero
Recommendation (the committee's words)
Besides traditional measures like apprenticeship quotas and community benefit funds, the Government should also investigate more creative mechanisms to ensure economic value from nuclear developments is captured locally. This could include doing more to encourage jointly consenting public infrastructure like roads and railways, and exploring fiscal measures like full business rate retention for local authorities. These approaches may prove more adaptable to SMRs, with their smaller geographic and economic footprint. (Recommendation, Paragraph 51)

From: Energy Security and Net Zero Committee, 4th Report - The new National Policy Statement for nuclear energy generation (HC 1212), 24 October 2025

Government response

The government responded to the whole report on 19 November 2025 (deadline 24 December 2025).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government welcomes parts of the Committee's report on EN-7, declines several recommendations including changes to section 2.4 and the Semi-Urban Population Density Criterion mapping, and makes a small number of specific commitments.

  • On regulatory duplication, it says it does "not share this assessment" of industry evidence, because the NSIP regime must judge project viability. On Recommendation 7 it believes the current section 2.4.5 "strikes the appropriate balance".
  • On guidance, it is developing supplementary information for EN-7 and says it "will publish the supplementary information shortly" and update it as lessons are learned.
  • On conditional commencement (Grampian conditions), it judges that explicit support in the NPS "is not required", but "can look at this again during future reviews of EN-7".
  • On the Semi-Urban Population Density Criterion, it proposes to keep the requirement to consult the HSE rather than publish a map, and says EN-7 "will be reviewed at least every 5 years".

Read the government's response ↗ Report an error