Source · SPSO (Scottish Public Services Ombudsman)

Angus Council

SPSO (Scottish Public Services Ombudsman) Partly Upheld Reference 201703550 Sector Local Government Category other Decided 01 June 2018

View Angus Council scorecard

Full decision

Summary

Mr C fell on a pedestrian railway crossing and injured himself. He complained to the council that they had not taken steps to ensure that the walkway was safe for members of the public, including providing adequate lighting and warnings of steps on the approach to the bridge. The council responded that they considered the footbridge was adequately maintained and that there was no obligation to provide lighting. Mr C was unhappy with this response and brought his complaint to us.

We found that the council had entered into an agreement with the rail company, and their predecessors, that stated the rail company was responsible for the maintenance of the footbridge. They were also responsible for specifying what lighting was required. Therefore, we determined that it was not the responsibility of the council to ensure that the footbridge was safe. We did not uphold this aspect of Mr C's complaint.

Mr C also complained that the council unreasonably failed to respond to his complaint. We found that the council's response was insufficient as it failed to explain that the rail company was responsible for the maintenance of the footbridge, and that they were the appropriate party to deal with the complaint. We also found that there was an unreasonable delay in providing Mr C with a response to his complaint. Therefore, we upheld this aspect of Mr C's complaint.

Recommendations

What we asked the organisation to do in this case: Apologise to Mr C for unreasonably failing to respond to his complaint and provide Mr C with a full explanation. The apology should meet the standards set out in the SPSO guidelines on apology available at https://www.spso.org.uk/leaflets-and-guidance.

In relation to complaints handling, we recommended: Complainants should be informed of any delays in providing a reponse ahead of the deadline set and revised timescales should be agreed.

We have asked the organisation to provide us with evidence that they have implemented the recommendations we have made on this case by the deadline we set.

Related reading

View Decision Report 201703550 as a PDF (12.89 KB) Updated: December 2, 2018

View original on SPSO (Scottish Publ… website

Other decisions involving Angus Council

Reference Date Summary Outcome
202200187 01 Jan 2024 C complained about the actions of the council in relation to repairs required at their home. They considered the communication, … Upheld
202005665 01 Nov 2021 C submitted a housing application to the council and complained about how this was handled. C complained that the council … Partly Upheld
202000613 01 Nov 2021 Prior to 2015, C’s grandchild was placed in their care by social work. C was granted a Section 11 Residence … Not Upheld
201907696 01 Feb 2021 C had a child (A). C was subject to a Pre-Birth Risk Assessment. The council put in place a rehabilitation … Not Upheld
201907845 01 Jan 2021 C, a support and advice worker, complained on behalf of their client (A) that the council had unreasonably failed to … Upheld