Source · SPSO (Scottish Public Services Ombudsman)

Loch Lomond and The Trossachs National Park Authority

SPSO (Scottish Public Services Ombudsman) Not Upheld Reference 201508565 Sector Local Government Category policy/administration Decided 01 August 2016

Full decision

Summary

Mrs C applied to the park authority for a repair grant; it was initially refused, but later an offer of funding was made. However, the park authority withdrew the offer of funding. Mrs C complained about this, and that the park authority would not change information they gave to applicants.

The park authority's conditions of grant stated that building work must not start before a signed copy of a grant offer has been received by the park authority, and that the park authority reserved the right to withhold the grant if any conditions were not complied with. As Mrs C's building work started before she was offered the grant, the park authority withdrew the offer. We found that while the timing of this was unfortunate from Mrs C's perspective, that did not invalidate the conditions of the grant.

The park authority explained that the circumstances in which funding became available to Mrs C were unusual, and they explained the importance of not raising applicants expectations falsely; we found these explanations were reasonable. In addition, the park authority said that, in future, they would consider Mrs C's point about the wording of their documentation where possible. We did not uphold Mrs C's complaints.

Related reading

View Decision Report 201508565 as a PDF (11.15 KB) Updated: March 13, 2018

View original on SPSO (Scottish Publ… website

Other decisions involving Loch Lomond and The Trossachs National …

Reference Date Summary Outcome
201700731 01 Sep 2018 Mrs C owns a property which is adjacent to a park owned by a community trust. A number of years … Not Upheld
201402300 01 Jun 2015 Mr C complained that Loch Lomond and The Trossachs National Park Authority failed to handle his planning application appropriately. He … Not Upheld
201406263 01 May 2015 Mr C complained that when assessing a planning application, the park authority failed to give priority to the primary aim … Not Upheld
View all decisions for this organisation