Scottish Water

SPSO (Scottish Public Services Ombudsman) Partly Upheld Reference 201302415 Sector Water Category sewer flooding - external Decided 01 March 2014

View Scottish Water scorecard

Full decision

Summary

Mr and Mrs C complained to Scottish Water about a blocked drain, but were told that the problem was theirs to resolve as the blockage was on their property. Mr and Mrs C instructed contractors, who established that the problem lay under the public footpath and was for Scottish Water to address. Scottish Water later confirmed this as correct. Mr and Mrs C requested that Scottish Water reimburse their costs, and complained about delay in completing the work. Scottish Water refused, however, to refund the costs on the grounds that they had no legal liability. They did, however, apologise for and explain the delay. Mr and Mrs C continued to pursue their complaint both with us and Scottish Water, who reviewed the circumstances and offered Mr and Mrs C 50 percent of their costs.

During our investigation we took into account all the relevant documentation and made further enquiries of Scottish Water. Our investigation found that the blockage causing problems was indeed under the public footpath and was for Scottish Water to resolve. However, accessibility to the drain from Mr and Mrs C's' side was complicated by an existing shaft. In the circumstances, Scottish Water said that they had no alternative but to ask Mr and Mrs C to address this, at their own cost, to allow access. However, we found that Scottish Water could have asked to do this work themselves or installed an access chamber from the public side of the blockage which, while it would have increased the time taken, would have been at Scottish Water's cost. While Scottish Water ultimately offered to reimburse 50 percent of costs, they were entirely responsible for the blockage under the public footpath. We upheld Mr and Mrs C's complaints about the costs and the handling of the complaint, but not about delay, for which we found the explanation reasonable.

Recommendations

We recommended that Scottish Water: repay the costs incurred; make a formal apology for the way in which the complaint was handled; and consider formulating a policy to cover circumstances where an ex-gratia payment may be required.

Related reading

View Decision Report 201302415 as a PDF (13.25 KB) Updated: March 13, 2018

View original on SPSO (Scottish Publ… website

Other decisions involving Scottish Water

Reference Date Summary Outcome
201903741 01 Oct 2021 C operated a bed and breakfast business from their home (the premises) and a number of years ago was identified … Not Upheld
201907203 01 Feb 2021 C complained that Scottish Water had failed to respond appropriately to a number of flooding incidents in their property. C … Not Upheld
201806416 01 Sep 2019 Mr C complained that Scottish Water (SW) delayed in reinstating a permanent water supply to his property and that their … Partly Upheld
201810639 01 May 2019 This summary is linked to case 201608499 in relation to Clear Business Water. Mr C complained to Clear Business Water … Upheld
201801415 01 Mar 2019 Mr C complained that Scottish Water had failed to resolve the flooding issues he was experiencing and that they had … Not Upheld
View all decisions for this organisation