SPSO (Scottish Public Services Ombudsman) Partly Upheld Reference 201203974 Sector Water Category policy/administration Decided 01 October 2014

View Scottish Water scorecard

Full decision

Summary

Mrs C made a number of complaints about Scottish Water. Firstly, she complained that they were incorrectly treating a pipe in her garden as a combined sewer pipe (in which domestic sewage is mixed with rainwater from roofs and paved surfaces, and transported to be treated). She also complained that they had refused to remove the pipe and her neighbour's connection to it, despite having no record of when and whether the connection had been approved. We obtained independent advice on the complaints from one of our water advisers, who said that the evidence indicated that it was reasonable for Scottish Water to say that the relevant pipe was a public combined sewer. In view of this, they were entitled to decide that they would not remove the pipe or the neighbour's connection to it.

Mrs C also complained that Scottish Water allowed untreated sewage and water drainage from another neighbour's property to accumulate in an emergency drainage chamber on her land. She provided photographs showing water and sewage in the manhole chamber. Our water adviser said that Scottish Water had a duty to maintain this and to ensure that any blockages were cleared. We found that, when Mrs C raised this with Scottish Water, they had confirmed this to be their responsibility, and fixed the problem. She also told us that they had caused flooding in her garden by allowing surface water from another property to enter a soakaway (a pit into which water flows and drains away). However, we found that they had no control over this. We did not uphold either of these complaints.

Mrs C also complained that Scottish Water carried out work on her land whilst she was on holiday, without giving the required notice. We found that Scottish Water had agreed the work with her, and had given her notice that contractors had been asked to carry it out. There was no evidence that the contractors carried out additional work that had not been agreed.

Finally, Mrs C complained that Scottish Water did not respond to her complaint promptly, and we found that they had delayed in concluding their investigation, so we upheld this aspect of the complaint. However, as they had already apologised to Mrs C for this we did not make any recommendations.

Related reading

View Decision Report 201203974 as a PDF (11.61 KB) Updated: March 13, 2018

View original on SPSO (Scottish Publ… website

Other decisions involving Scottish Water

Reference Date Summary Outcome
201903741 01 Oct 2021 C operated a bed and breakfast business from their home (the premises) and a number of years ago was identified … Not Upheld
201907203 01 Feb 2021 C complained that Scottish Water had failed to respond appropriately to a number of flooding incidents in their property. C … Not Upheld
201806416 01 Sep 2019 Mr C complained that Scottish Water (SW) delayed in reinstating a permanent water supply to his property and that their … Partly Upheld
201810639 01 May 2019 This summary is linked to case 201608499 in relation to Clear Business Water. Mr C complained to Clear Business Water … Upheld
201801415 01 Mar 2019 Mr C complained that Scottish Water had failed to resolve the flooding issues he was experiencing and that they had … Not Upheld