Mr C complained about the council's handling of two planning applications for the construction of a new house on a plot of land neighbouring his home.

Planning permission was initially granted for the build, despite the council's failure to notify neighbours of the development as required by planning regulations. Although the developer had the council's permission to build the new house, this was vulnerable to legal challenge due to this failure to notify neighbours.

To remedy this, the developer submitted a new planning application so that neighbour notification could be carried out. Planning permission was subsequently approved again.

Mr C felt that the original planning permission should have been revoked while the second application was being considered. He believed that the failure to do this meant that any objections submitted would be dismissed in favour of confirming the existing planning permission. Mr C submitted objections based on the impact the new development would have on his own property's privacy. He did not feel that his objections were taken into account when planning permission was granted for a second time.

We upheld Mr C's complaint that the council granted planning permission without neighbour notification. However, we did not find it necessary for the original planning permission to be revoked while the resubmitted planning application was being considered. The planning officer's report showed that due consideration was given to Mr C's objections with reference to local planning policy and we were, therefore, generally satisfied that the second planning application had been properly processed.

Mr C was told by the planning committee's vice convenor that he would be invited to attend a pre-determination hearing. This did not happen and he was subsequently told that planning permission had been granted without his attendance at such a meeting. On looking at this issue, we found that it was beyond the vice convenor's powers to make this promise to Mr C. However, there was no obligation on the council to hold a pre-determination hearing for this planning application or to invite Mr C to it. We recommended that the council remind elected members of the process for notification of and invitation to pre-determination hearings.

Mr C raised further concerns about the council's handling of his formal complaint. We found that the complaint was properly investigated but that there were delays to the council's responses.

Recommendation We recommended that the council: • remind elected members of the process for notification of and invitation to pre-determination hearings.

Related reading

View Decision Report 201101677 as a PDF (23.91 KB) Updated: March 13, 2018

View original on SPSO (Scottish Publ… website

Other decisions involving The City of Edinburgh Council

Reference Date Summary Outcome
202505687 01 Jun 2026 C complained to the council about damp and mould in their rental property. C had been moved to the property … Upheld
202404014 01 Feb 2026 C complained that the council did not properly consider their concerns about work being carried out on a neighbour’s summerhouse … Not Upheld
202302915 01 Apr 2025 A & B complained to the council about their handling of their claims procedure in relation to the Trams to … Upheld
202303840 01 Oct 2024 C is the grandparent of A and B, whose parents were separated. C complained about the actions of the council … Partly Upheld
202301380 01 Aug 2024 C complained about the council’s social work service during the pre-adoptive process of their child (A). C complained about the … Partly Upheld
View all decisions for this organisation