Source · SPSO (Scottish Public Services Ombudsman)

Lothian NHS Board

SPSO (Scottish Public Services Ombudsman) Upheld Reference 201101077 Sector Health Category Appointments/Admissions (delay, cancellation, waiting lists) Decided 01 January 2012

View NHS Lothian scorecard

Full decision

Summary

Mr C first visited his GP in September 2009 with pain and swelling in his testicles and was referred to the urology team at the Western General Hospital. He was placed on a waiting list for treatment. He was seen in January 2010 by two specialists who could not agree a diagnosis and referred for a scan which was done in February. In March he was seen by another urologist and told that his problem was not a urology one. Mr C was referred back to the general surgical department and in April 2010 he received a letter telling him that he was on the waiting list to see a consultant.

Mr C telephoned the department to complain about this further delay but was told that nothing could be done. Mr C was seen in July 2010 in the colorectal department and referred for an MRI scan. He was seen again there in September 2010 and a hernia was diagnosed. Mr C was told that due to his other complex health difficulties, the remedial surgery he required would have to be done at another hospital by a specific surgeon. Mr C was seen there in November 2010 and had his surgery in January 2011. Mr C was dissatisfied with the wait for surgery which totalled some 64 weeks and the resultant increase in pain and discomfort he had to endure.

We upheld Mr C's complaint. We found that his wait for surgery had been excessive. There were a number of things that could have been done differently which would have reduced his waiting time. A CT scan was first considered in March 2010, but was not performed until August 2010. Mr C was reviewed by two registrars, who could have discussed his case with a consultant, given there were clear diagnostic difficulties. It was not until November 2010, over a year after Mr C had first been referred, that a consultant took responsibility for the management of his care. We also found the board's responses to Mr C's letters of complaint to be insufficient.

Recommendation We recommended that the board provide a full apology to Mr C for the delay he experienced when waiting to undergo his operation.

Related reading

View Decision Report 201101077 as a PDF (19.97 KB) Updated: March 13, 2018

View original on SPSO (Scottish Publ… website

Other decisions involving Lothian NHS Board

Reference Date Summary Outcome
202404449 01 Jan 2026 C complained about the care that their adult child (A) received from the prison healthcare team and particularly a failure … Upheld
202304800 01 Mar 2025 C complained that the board failed to provide reasonable personal care and treatment to their sibling (A). A was admitted … Upheld
202304367 01 Dec 2024 C complained on behalf of their spouse (A) about the standard of care and treatment received in the months before … Partly Upheld
202005296 01 May 2022 C complained that there had been an unreasonable delay in their late parent (A) receiving a prescription of antibiotics following … Upheld
202002582 01 Jan 2021 C complained about the clinical care provided to their child (A) by the board, specifically, that a Chiari malformation (where … Not Upheld
View all decisions for this organisation