Addressee: Home Office · Source location: Page 10, paragraph 20, point a
The Department should:
a) Clarify immediately the respective roles and responsibilities of the Home Office and the police for delivery of the new service, particularly on decision-making authority at key stages.
Response position:
Accepted
Delivery:
Implemented
· 07/2021
· Confirmed by NAO
Addressee: Home Office · Source location: Page 10, paragraph 20, point b
b) Agree a revised business case for the programme that covers its whole lifecycle, with central government stakeholders and funders including the police.
Response position:
Accepted
Delivery:
Implemented
· 07/2021
· Confirmed by NAO
Addressee: Home Office · Source location: Page 10, paragraph 20, point c
c) Set out a clear programme plan, including delivering the first product to the police during 2021, and outline plans beyond that which demonstrate how NLEDS will replace the PNC’s capabilities in the time required (by 2025-26). It should also include the key dependencies for the programme’s delivery, particularly how police forces will transition from the PNC toNLEDS.
Response position:
Accepted
Delivery:
Implemented
· 08/2023
· Confirmed by NAO
Addressee: Home Office · Source location: Page 10, paragraph 20, point d
d) Produce plans setting out how it will guarantee a continuing PNC service that the police can rely on until NLEDS is ready, including a full assessment of the risks of continuing to run the PNC and contingency plans for failure. This plan should include a review point at which the decision to replace the PNC’s operating system can be taken promptly.
Response position:
Accepted
Delivery:
Implemented
· 04/2022
· Confirmed by NAO
Addressee: Home Office · Source location: Page 10, paragraph 20, point e
e) Monitor its technical capability and skills to deliver the programme, and urgently address any shortfalls.
Response position:
Accepted
Delivery:
Implemented
· 09/2023
· Confirmed by NAO
Addressee: Home Office · Source location: Page 10, paragraph 20, point f
f) In procuring new suppliers, consider carefully the balance of risks and incentives between the Department and suppliers, and how it will integrate the work of different suppliers, in order to deliver the new services to an assured timetable.
Response position:
Accepted
Delivery:
No longer relevant
· 09/2022
· Confirmed by NAO