Source · National Audit Office

Public chargepoints for electric vehicles

Public electric vehicle chargepoint installations are on track, but government needs to make sure they are located in the right places.

Published: 13 Dec 2024 Recommendations: 5 Type: Value for Money NAO confirmed: 5 Department: Department for Transport
Dept: Department for Transport Topics: Driving and road transportEnergy and environmentEnergy infrastructureTransport nao.org.uk →

Recommendations

5 items
5 accepted 2 implemented 3 in progress

Recommendation 1

Addressee: Department for Transport · Source location: Page 13, paragraph 19, point a

DfT should consider whether developing regional demand forecasts, and demand forecasts differentiating between urban and rural locations, would aid the rollout of public chargepoints.

Response position: Accepted

Delivery: In progress · Awaiting opportunity · Confirmed by NAO

Recommendation 2

Addressee: Department for Transport · Source location: Page 13, paragraph 19, point b

DfT should develop a set of strategic principles for intervention, to guide its design of future interventions where chargepoint demand may not be addressed by its existing programmes.

Response position: Accepted

Delivery: Implemented · Q1 2025-26 · Confirmed by NAO

Recommendation 3

Addressee: Department for Transport · Source location: Page 13, paragraph 19, point c

DfT should work with local authorities, and the central support body it established to help them, to develop a plan for how to sustain the capability built through the LEVI programme after it ends.

Response position: Accepted

Delivery: Implemented · Q3 2024-25 · Confirmed by NAO

Recommendation 4

Addressee: Department for Transport · Source location: Page 13, paragraph 19, point d

DfT should develop a monitoring framework for the open data it collects through the Public Charge Point Regulations, so that it can understand emerging consumer and operator issues in the chargepoint market, including where regional variations may emerge.

Response position: Accepted

Delivery: In progress · Q3 2026-27 · Confirmed by NAO

Recommendation 5

Addressee: Department for Transport · Source location: Page 13, paragraph 19, point e

DfT should ensure that a clear understanding of what constitutes compliance to the chargepoint accessibility standard is determined, so that industry and local authorities can incorporate it into future installations.

Response position: Accepted

Delivery: In progress · Q2 2027-28 · Confirmed by NAO