Ministry of Defence Major Projects Report 2005

Published: 25 Nov 2005 Type: Value for Money

The National Audit Office’s annual report on the top 20 defence equipment projects shows that, in the last year, the forecast cost has actually decreased by £700 million but on average each project has been delayed by two and a half months. The delays are mainly due to technical problems in three projects: CIP (which […]