Source · National Audit Office

Managing and replacing the Aspire contract

Published: 22 Jul 2014 Type: Value for Money Department: HM Revenue and Customs

There are serious risks to HMRC’s business if the programme to replace the Aspire contract fails to meet its objectives by June 2017, when the contract ends.

Dept: HM Revenue and Customs Topics: Commercial and financial managementCommercial and regulationDigital servicesDigital transformationDigital, data and technologyMoney and taxProcurement and contract managementTax and revenue nao.org.uk →

Public Accounts Committee follow-up

1 report

The Public Accounts Committee examined this NAO report and published its own recommendations. The government responds to PAC recommendations via Treasury Minutes.