Decommissioning Sellafield: managing risks from the nuclear legacy

Sellafield nuclear site is not yet achieving value for money due to concerns over project management, the pace of delivery and staffing.

Published: 23 Oct 2024 Recommendations: 4 Type: Value for Money NAO confirmed: 4 Department: Department for Energy Security and Net Zero
Dept: Department for Energy Security and Net Zero Topics: Energy and environmentNuclear power nao.org.uk →

Recommendations

4 items
4 accepted 1 implemented 3 in progress

Recommendation 1

Addressee: Nuclear Decommissioning Authority · Source location: Page 12, Recommendation a (following paragraph 21).

Sellafield should: develop an approach that demonstrates to stakeholders that effective progress is being made towards decommissioning the site. This should cover enabling activities and include progress to date at Sellafield, while also supporting future funding choices and Spending Review decisions

Response position: Accepted

Delivery: In progress · Q4 2026-27 · Confirmed by NAO

Recommendation 2

Addressee: Nuclear Decommissioning Authority · Source location: Page 12, Recommendation b (below paragraph 21)

Sellafield should: carry out an assessment of the culture across the site and develop suitable metrics to assess and monitor whether all areas of the site and its leadership are positively contributing to creating a high performing public sector organisation.

Response position: Accepted

Delivery: Implemented · Q4 2025-26 · Confirmed by NAO

Recommendation 3

Addressee: Department for Energy Security and Net Zero; HM Treasury; Nuclear Decommissioning Authority · Source location: Page 12, Recommendation d (below paragraph 21)

HM Treasury should consider what information and evidence it would need from the NDA group to be able to consider longer term settlements. The NDA should explore whether longer-term budgets for Sellafield are feasible

Response position: Accepted

Delivery: In progress · Q4 2026-27 · Confirmed by NAO

Recommendation 4

Addressee: Nuclear Decommissioning Authority · Source location: Page 12, Recommendation c (below paragraph 21)

The Nuclear Decommissioning Authority, with its group subsidiaries, should: develop measures to assess the operational effectiveness of its sites. In particular, it should monitor whether Sellafield is maintaining the capability needed to continue to operate safely and deliver progress with the mission.

Response position: Accepted

Delivery: In progress · Q3 2026-27 · Confirmed by NAO

Public Accounts Committee follow-up

1 report

The Public Accounts Committee examined this NAO report and published its own recommendations. The government responds to PAC recommendations via Treasury Minutes.