Published: 3 May 2019 Recommendations: 5 Type: Value for Money NAO confirmed: 5 Department: Department for Transport

This report examines the causes of the cost increases and delays to the Crossrail programme.

Dept: Department for Transport Topics: Commercial and financial managementCommercial and regulationProcurement and contract managementTransport nao.org.uk →

Recommendations

5 items
5 accepted 5 implemented
Rec Recommendation Addressee Acceptance Implementation
1
For the Crossrail programme: a) Crossrail Ltd should continue to refine its plan to complete the programme, establish a realistic cost estimate, and resist external attempts to influence timetable and cost.
Ref Page 9, point a · Implemented 08/2020
Crossrail Ltd Accepted Implemented ✓ NAO
2
b) Crossrail Ltd, working with sponsors, should establish a range of scenarios that set out the potential future impacts on the taxpayer, passengers and businesses and develop plans for how further cost increases or delays in collecting revenue will be financed.
Ref Page 9, point b · Implemented 12/2020
Crossrail Ltd Accepted Implemented ✓ NAO
3
c) Crossrail Ltd should rebuild its capacity and capability to complete the programme in a timely and cost-effective way.
Ref Page 9, point c · Implemented 08/2020
Crossrail Ltd Accepted Implemented ✓ NAO
4
For the Department’s other current and future major programmes: d) We note that the Department has completed a lessons learned exercise and we would encourage it to also apply the lessons to other major projects including High Speed 2.
Ref Page 9, point d · Implemented 04/2019
Department for Transport Accepted Implemented ✓ NAO
5
RfLi should set out a plan to realise and monitor the benefits of running a fully digital railway.
Ref Page 12, point e · Implemented 07/2023
Rail for London Infrastructure Accepted Implemented ✓ NAO