9

Date for submitting Safety Cases

Piper Alpha Inquiry · The Public Inquiry into the Piper Alpha Disaster · Issued 12 November 1990

Government responseNot tracked (historical inquiry)

DeliveryNo statement from the addressee found

Recommendation, verbatim from the inquiry

●Inquiry recommendation, Recommendation 9

As regards existing installations the date for submission of the Safety Case should be laid down by regulation. There is an urgent need for the submission of Safety Cases, but the date should be selected by the regulatory body. The regulatory body should have the power, in the event of the failure of an operator to submit an acceptable Safety Case, to require the operator to take whatever remedial action it considered necessary, including requiring the installation to be shut down (paras 17.44-45).

Piper Alpha Inquiry, The Public Inquiry into the Piper Alpha Disaster · 12 Nov 1990 Source PDF, page 389 →

Government response

●No formal government response recorded

The Index has not yet recorded a verbatim government response to this recommendation.

Delivery

No statement on delivery from the addressee has been found in the sources searched. This is separate from the response above.

How this page is built

The recommendation and the government responses are verbatim from primary documents. Delivery statements and other bodies' findings are shown in their own words, each with its source. The summary is written by this site and labelled as such. The Index does not paraphrase sources or characterise intent; it records what has been published.