Review E Wing suitability for vulnerable detainees
Brook House Inquiry · The Brook House Inquiry Report · Issued 19 September 2023 · Addressed to: Home Office
Government responseHome Office: Accepted, fully or in part (not specified) (Jan 2025)
DeliveryHome Office says in progress (Jan 2025)
Recommendation, verbatim from the inquiry
●Inquiry recommendation
The Home Office and the current operator of Brook House must keep under review the appropriateness of the multi-purpose use of E Wing, particularly in relation to its suitability as a location to detain vulnerable people.
Brook House Inquiry, The Brook House Inquiry Report · 19 Sep 2023 Source PDF →
Published evidence summary
AI-generated evidence summary
In January 2025, Dame Angela Eagle, Minister of State at the Home Office, stated in a written parliamentary answer that the recommendation to review the suitability of E Wing for vulnerable detainees was accepted or partially accepted, and was "due for closure by the end of January 2025" (Dame Angela Eagle response, Jan 2025; Dame Angela Eagle, Jan 2025). The record holds no update since the Home Office's response of January 2025 (Dame Angela Eagle response, Jan 2025; Dame Angela Eagle, Jan 2025).
AI-generated summary of the record on this page, checked by a second model and automatic checks, 26 Sep 2026.
Government response
●Home Office · Accepted, fully or in part (not specified) · 15 Jan 2025
30 out of the 33 recommendations made by the Brook House Inquiry have been accepted or partially accepted.
Response document: Mistreatment of Detainees at Brook House Immigration Removal Centre Inquiry (written question UIN 23170)
Earlier statement from Home Office (1)
●Home Office · Under consideration · 19 Mar 2024
6.5.2. The multi-purpose use of Eden Wing at Brook House, and any potential risks associated with co-location of vulnerable individuals with those who may have been removed from association, is under consideration. Any learning will be applied across the removal estate.
Extract from: Government response to the public inquiry into Brook House Immigration Removal Centre
Delivery
●Home Office says in progress · 15 Jan 2025
5 (recommendations 5, 11, 27, 28 and 29) due for closure by the end of January 2025
How this page is built
The recommendation and the government responses are verbatim from primary documents. Delivery statements and other bodies' findings are shown in their own words, each with its source. The summary is written by this site and labelled as such. The Index does not paraphrase sources or characterise intent; it records what has been published.