Merseyside Passenger Transport Authority
Other• The authority confirmed it would include rumble strips within the white lines in the area concerned. • It proposed to engage a suitable contractor by 5 May 2017. • The authority stated it would endeavour to complete the works at the earliest opportunity and provide further updates on start and completion dates.
View full response
“Please accept our apologies for not responding to Mr Rebello’s Order of 28th February 2017. We were unaware of the Order or any recommendations within it. However, having liaised with (Head of Asset Management) this afternoon, I can confirm that we are able to comply with Mr Rebello’s recommendations for rumble strips to be included within the white lines in the area concerned. In respect of a timetable for action, we propose to engage a suitable contractor by the end of next week, being 5 th May
2017. We will then endeavour to have the works completed at the earliest opportunity taking into account the availability of the contractor/closure of the Tunnel approach roads and seeking permissions from Wirral Borough Council. If this is acceptable to Mr Rebello, once we have instructed a suitable contractor, we will advise further with a start and completion date for the works.”
André Rebello OBE Senior Coroner Liverpool and Wirral Area Hon Secretary Coroners’ Society of England & Wales HM Coroner’s Court Gerard Majella Courthouse Boundary Street Liverpool L5 2QD
2/5/26, 2:39 PM RE: Preventing Future Deaths
1/3