Select committee: Defence Committee
Conclusion 125
First Report - Ready for War?
Published 4 Feb 2024
Addressed to Ministry of Defence
Defence Committee Armed Forces Readiness All items in this report Report on parliament.uk ↗ Inquiry on parliament.uk ↗
Conclusion (the committee's words)
Professor Clarke warned us in April 2023 that the implications of the Ukraine war were “taking time to filter through to Governments.”251 One of the most obvious examples of this is the length of time it took to conclude a contract for an increase in production of 155 mm artillery shells.252 This is despite regular pleas from Ukraine for these shells in the Spring of 2023.253 It was first reported that the Government had issued a letter of intent (telling industry that it intended to purchase more artillery shells) in November 2022254 but it took 9 months of negotiation before a contract was finally signed in July 2023.255 When we raised this with the Minister for the Armed Forces, he told us that the delay had been caused by the lack of a “going-concern production line and there was some debate about how the manufacturing capacity was going to be funded”. The contract, when agreed, was a multi-year contract which specified a number of shells to be delivered each year ensuring the long-term viability of the production line, but the Minister acknowledged that it had demonstrated a need to change the way in which the MOD approaches procurement.256 There are possible lessons to be learned from the pace at which our US allies have increased capacity and production. Box 5: Timelines of contracting for NLAWs and 155 shells NLAW • Letter of intent presented to Saab as Authorisation to Proceed: September 2022 • Contract to Saab: 7 December 2022 • Delivery from July 2023 155 Shells • Letter of intent presented to BAE as Authorisation to Proceed: November 2022 • Contract to BAE: 11 July 2023 • Delivery: Q1 2025 Source: Compiled by Defence Committee staff
From: Defence Committee, First Report - Ready for War? (HC 26), 4 February 2024
Government response
The government responded to the whole report on 25 April 2024 (deadline 4 April 2024).
Summary written by Accountability Index from the government's response. It is not the government's own words.The government agrees there is no regular mechanism to scrutinise readiness and offers an annual open session, releases some Defence Planning Assumptions headlines, and sets out its position on stockpiles, recruitment and procurement.
- On transparency, the government "recognises that the Committee should have public access to more information on planning assumptions and readiness" and releases headlines from the 2023 assumptions, committing to release "as much as possible" of the next iteration "when national and NATO planning processes have matured".
- It agrees the response time for the inquiry was slow and "will make every effort to ensure this is not repeated".
- On the £1.95bn from the Spring Budget 2023, it states the money "will be spent in full on measures to address gaps in our capabilities". It says exact stockpile holdings are "not releasable on the grounds of national security".
- On recruitment and retention, it says a formal response to each Haythornthwaite Review recommendation "will be published during 2024", with next steps for delivery and implementation for each.