Select committee: Defence Committee

Conclusion 9

Ninth Report - It is broke — and it’s time to fix it: The UK’s defence procurement system Published 16 Jul 2023 Paragraph 111
Conclusion (the committee's words)
The Ministry of Defence’s relationship with industry leaves much to be desired. The Ministry of Defence and DE&S should engage in more consistent dialogue with industry. This should include a formalised pre-procurement stage (at appropriate classification levels) regarding future requirements and their feasibility.

From: Defence Committee, Ninth Report - It is broke — and it’s time to fix it: The UK’s defence procurement system (HC 1099), paragraph 111, 16 July 2023

Government response

The government responded to the whole report on 20 September 2023 (deadline 16 September 2023).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government does not agree that the procurement system is broken, but accepts "the need for reform" and sets out reform work already under way across Defence.

  • On the Committee's P75 recommendation, it agrees there is "a strong argument" for higher probability figures for schedule approval of complex programmes, and has issued guidance making P70 "the norm on schedule" for Government Major Projects Portfolio programmes. It says approval at a higher P value "will not improve project performance".
  • It agrees on the need for more consistent dialogue with industry and on "an increased emphasis on time", but says it "would therefore not be desirable" to use the Urgent Capability Requirements approach across the whole defence portfolio.
  • On accountability, it "recognises the need to clarify internal accountabilities", and says this will be addressed in the Defence Operating Model review. It says "active consideration" is being given to the CEO of DE&S joining the Defence Board.
  • On SRO tenure, it notes there is "no formal mechanism" to keep an individual in post for five years, but says it continues to explore how to use available levers such as performance pay and pivotal role allowances.

Read the government's response ↗ Report an error