The Triples Review revealed serious administrative failings in the handling of ARAP applications from former members of Afghan specialist units who had worked closely with UK forces. The high overturn rate showed that earlier determinations that applicants were not eligible for relocation could not be treated as reliable. The government therefore has a special responsibility to former Triples whose applications were wrongly refused and who, because of those failings and subsequent delay, may have spent additional years in hiding or been left to make their own way to a third country. (Conclusion, Paragraph 199) 72
From: Defence Committee, 1st Report - Shifting heaven and earth? The Afghan data breach and resettlement schemes (HC 69), 30 July 2026
Government response
The government responded to the whole report on 16 October 2026 (deadline 30 September 2026).
Summary written by Accountability Index from the government's response. It is not the government's own words.The Ministry of Defence says the data incident was "unacceptable", accepts a number of the Committee's conclusions and some recommendations in whole or in part, and declines others, citing risk to life and national security.
- On the injunction, the government agrees the super-injunction was exceptional and accepts Recommendation 8 "in principle", but says any decision to widen briefing would be "for the government of the day".
- It "accepts part of" the recommendation to publish principles on injunctions, saying any course of action "remains a decision for Ministers" and is to be considered case by case.
- It will provide the Committee with "six-monthly updates" on the Afghan Resettlement Programme and expects to complete all ARP casework by Spring 2027, though the August 2026 milestone for initial decisions was missed.
- It declines to publish quality assurance KPIs, saying they "could have unintended consequences", and says exceptional circumstances will be considered for those unable to self-move within 12 months.