Recommendation (the committee's words)
The government should, in response to this report, publish the lessons it has learned from the Afghan data-breach injunction and set out clear principles governing when it or any other public body may exceptionally seek an injunction preventing disclosure of a matter of widespread public interest. Those principles should include requirements for: periodic reassessment of necessity and proportionality against recorded criteria; controlled external challenge at the earliest safe stage; minimum expectations for parliamentary notification; arrangements for audit and Accounting Officer assurance; and clear ministerial accountability for applications to maintain, vary or discharge the injunction. (Recommendation, Paragraph 106)
From: Defence Committee, 1st Report - Shifting heaven and earth? The Afghan data breach and resettlement schemes (HC 69), 30 July 2026
Government response
The government responded to the whole report on 16 October 2026 (deadline 30 September 2026).
Summary written by Accountability Index from the government's response. It is not the government's own words.The Ministry of Defence says the data incident was "unacceptable", accepts a number of the Committee's conclusions and some recommendations in whole or in part, and declines others, citing risk to life and national security.
- On the injunction, the government agrees the super-injunction was exceptional and accepts Recommendation 8 "in principle", but says any decision to widen briefing would be "for the government of the day".
- It "accepts part of" the recommendation to publish principles on injunctions, saying any course of action "remains a decision for Ministers" and is to be considered case by case.
- It will provide the Committee with "six-monthly updates" on the Afghan Resettlement Programme and expects to complete all ARP casework by Spring 2027, though the August 2026 milestone for initial decisions was missed.
- It declines to publish quality assurance KPIs, saying they "could have unintended consequences", and says exceptional circumstances will be considered for those unable to self-move within 12 months.