Source · Select Committees · Built Environment Committee

Recommendation 190

190

This interpretation of the law could mean that, in some cases, a permission already given...

Conclusion
This interpretation of the law could mean that, in some cases, a permission already given will be lost because tests that did not apply at the time that it was granted have been applied retrospectively. As the Ministerial statement made clear, this means that “… development that previously was lawfully screened out at the permission stage cannot now be screened out.” 244
Government Response

A response document is linked to this report, dated 12 December 2023. Response attribution to this conclusion has not been verified. Read the response document ↗