Conclusion 20
Nineteenth Report - MoD Equipment Plan 2023–2033
Published 8 Mar 2024
Addressed to HM Treasury
Public Accounts Committee The Equipment Plan 2023–2033 All items in this report Report on parliament.uk ↗ Inquiry on parliament.uk ↗
Conclusion (the committee's words)
Only two of the 46 MoD equipment projects that are included in the Government Major Projects Portfolio (GMPP) are rated as being highly likely to be delivered to time, budget and quality (green).60 Successful delivery appears to be unachievable for five GMPP projects (red), including replacement communications technology, nuclear submarine reactors, and missiles.61 The rest of the GMPP projects are rated amber, which means that delivery appears feasible, but there exist significant issues requiring management attention.62 The MoD told us that it has introduced several initiatives to address this, including regular GMPP review meetings, started by the Minister for Defence Procurement, which focus on red- and amber-rated projects, and project review meetings led by non-executive directors on the board of Defence Equipment & Support.63
From: Public Accounts Committee, Nineteenth Report - MoD Equipment Plan 2023–2033 (HC 451), 8 March 2024
Government response
The government responded to the whole report on 28 May 2024.
Summary written by Accountability Index from the government's response. It is not the government's own words.The government agrees with the Committee's recommendations on consistent forecast costing, clearer signals to industry, assessing the new procurement model and reliance on allies, but disagrees with those on setting out cuts under a 2.5% shortfall and on reporting nuclear funding trends.
- On the 2.5% of GDP aspiration, the government disagrees with the recommendation; the department "does not intend to set out a list of capabilities that would be cut" because this would risk operational security and industry confidence.
- On nuclear costs, the government disagrees with the recommendation. If conventional budgets are affected by nuclear funding needs the department "will make that clear", but it considers going further "wholly speculative".
- The government agrees that all budget holders should treat forecast costs consistently, with a target implementation date of Spring 2025. The department "will seek to standardise" the data and its presentation.
- The government agrees to assess the impact of the Integrated Procurement Model, with a target date of December 2024. It will "monitor the increase in pace of delivery and provide updates as appropriate".