Conclusion 21

Thirty-Eighth Report - Rail reform: The rail transformation programme Published 27 May 2024 Addressed to HM Treasury
Conclusion (the committee's words)
Reviews by the IPA and the Department in early 2023 found that the Rail Transformation Board’s governance was confused, accountabilities unclear, and there was not agreement across stakeholders on the scope and delivery approach of the Programme. The Department recognises that there will be a challenge in getting stakeholders to prioritise work intended to improve rail before the timing of future reform is clearer.45 It told us that it has created a rail reform board which has the right people around the table, with very clear accountabilities, both for individual projects and within its wider departmental governance.46 39 Q 49–52 40 C&AG’s Report, para 2 41 Q 36; C&AG’s Report, para 9, para 2.8 42 Q 28–20 43 Q 36 44 Q 79 45 C&AG’s Report, paras 9, 3.9 46 Q 19 14 Rail reform: The rail transformation programme Engaging with the workforce

From: Public Accounts Committee, Thirty-Eighth Report - Rail reform: The rail transformation programme (HC 652), 27 May 2024

Government response

The government responded to the whole report on 11 July 2025 (deadline 27 July 2024).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government states that it "agrees with the Committee's recommendation" on each of the six recommendations, with target implementation dates ranging from Winter 2024 to Spring 2025, and one marked as already implemented.

  • On delivering reform, it states the department is "remobilising" and preparing for the mobilisation of shadow Great British Railways, and will "set out next steps shortly". Further legislation to create GBR was announced in the King's Speech.
  • On passenger focus, it says GBR will be "incentivised by targets and performance criteria set by the Secretary of State", and a new Passenger Standards Authority will independently monitor standards.
  • On subsidy and value for money, the department "expects to see these reforms delivered over the course of this parliamentary term" as legislation is enacted and private operators move into public ownership. The target implementation date given is Spring 2025.
  • On accessibility, it says the department "will set out next steps as soon as possible" and will use accessibility audit data from all 2,575 stations to target future investment decisions.