Select committee: Public Accounts Committee

Conclusion 5

Thirty-Fifth Report - Supporting mobile connectivity Published 28 May 2024 Addressed to HM Treasury
Conclusion (the committee's words)
The Department lacks up to date information to track progress on whether the Shared Rural Network programme will meet its targets for increasing connectivity on roads and premises. In addition to the overall target to increase 4G coverage to 95% of the UK landmass, the Department also aims to provide 280,000 additional premises and 16,000 kilometres of roads with 4G coverage through the Shared Rural Network programme. However, the Department is unclear on how many premises and roads had gained 4G connectivity so far and is still in discussions with the mobile network operators about getting the information it needs to track progress against these targets. Furthermore, it says that Ofcom will not assess whether the mobile network operators have met these targets until 2027. Despite not being able to confirm what progress has been made do far, based on information BDUK has received to date from the mobile network operators, the Department says it is confident that it will meet the roads and premises targets. Recommendation 5: The Department should work with Ofcom and the mobile network operators to ensure that it can report publicly on progress against its targets for increasing 4G connectivity on roads and premises.

From: Public Accounts Committee, Thirty-Fifth Report - Supporting mobile connectivity (HC 650), 28 May 2024

Government response

The government responded to the whole report on 11 July 2025 (deadline 28 July 2024).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government states that it "agrees with the Committee's recommendation" on each of the seven recommendations in the report, giving target implementation dates between December 2024 and January 2027.

  • On cost certainty, the government says the grant structure "moves the majority of the financial risk for delivery outside government" and that a capped fund for the Total Not Spot element means its contribution "cannot exceed £300.7 million".
  • On areas left without 4G, the government says it "is not possible to predict with a high degree of certainty" which areas these will be at this stage; identification will be undertaken "upon completion of the site acquisition phase". Target date: January 2027.
  • On coverage data, the department "will ask that Ofcom examines any cases where areas have lost all mobile connectivity following 3G switch off" and will work with Ofcom to "consider other ways that consumers can report gaps in coverage". Target date: January 2025.
  • On 5G, the government says standalone 5G is commercially funded "with no government subsidy", and that it will provide an evaluation of the Open Networks Programme and 5G Innovation Regions "following their conclusion in 2025".

Read the government's response ↗ Report an error