Conclusion 17

76th Report - New Hospital Programme update Published 22 Apr 2026 Addressed to HM Treasury
Conclusion (the committee's words)
We asked the Department whether it had mechanisms in place to capture any unexpected downsides of the design. The Department responded that it would identify adverse consequences through its oversight regime. NHS England added that it will be easier to identify downsides where it has hard metrics, and that it is keen to improve their data and real-time analysis.34 The Department subsequently wrote to us with additional information on how it plans to assess and monitor the benefits of the Hospital 2.0. design. It is developing a standard operating model to help trusts identify benefits and the associated impact on revenue and workforce requirements. It is also developing benefits management plans to monitor realised benefits and potential downsides.35

From: Public Accounts Committee, 76th Report - New Hospital Programme update (HC 1705), 22 April 2026

Government response

The government responded to the whole report on 4 August 2026 (deadline 22 June 2026).

Read the government's response ↗ Report an error