Select committee: Public Accounts Committee

Conclusion 19

51st Report - The UK’s F-35 stealth fighter capability Published 31 Oct 2025 Addressed to HM Treasury
Conclusion (the committee's words)
The Department accepted that accommodation at RAF Marham is not good enough, reflecting wider problems within the Defence estate, more than half of which is over 50 years old. The Department told us that it had identified the need for increased investment in accommodation in the Strategic Defence Review and is working through investment choices as part of the Defence Investment Plan. The Chief of the Defence Staff told us that the Royal Air Force has committed to upgrading all its accommodation in the lowest two categories so that it meets the criteria for the highest two categories. Across the whole Royal Air Force estate this will cost more than £1.5 billion over approximately 15 years.40

From: Public Accounts Committee, 51st Report - The UK’s F-35 stealth fighter capability (HC 1232), 31 October 2025

Government response

Latest Treasury Minutes progress report to the Committee of Public Accounts on the Fifty-first Report of Session 2024-26

The government responded to the whole report on 4 June 2026 (deadline 31 December 2025).

Read the government's response ↗ Report an error

Treasury minutes: Government response to the Committee of Public Accounts on the Fifty-first report from Session 2024-26

Published 19 January 2026.

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government agrees with most of the Committee's recommendations on the F-35, disagreeing on a F-35-specific workforce plan and on updating the Committee on Dual Capable Aircraft costs.

  • On Full Operating Capability, the government agrees that criteria should take account of capability gaps and sustainment, with a target implementation date of November 2026.
  • It agrees to write to the Committee by 30 April 2026 on increasing F-35 availability, saying the longer timeline is needed to draw on lessons from Carrier Strike Group 25.
  • It disagrees with producing an F-35-specific recruitment and retention plan and will instead address the issue through the "ongoing RAF People Campaign".
  • On RAF Marham accommodation, it will write by 31 May 2026 to advise "whether" the current timescale can be brought forward, after infrastructure requirements are reassessed following the Defence Investment Plan.

Read the government's response ↗ Report an error