Source · Select Committees · Public Accounts Committee
Recommendation 9
9
Lack of investment has also resulted in severe maintenance backlogs within the prison estate.
Conclusion
Lack of investment has also resulted in severe maintenance backlogs within the prison estate. As at April 2019, HMPPS had around 63,200 outstanding maintenance jobs. HMPPS also estimated that it would cost £916 million to address its backlog of major capital works. It forecasts that it will need to spend £194 million each year over the next 25 years for maintenance costs. We asked it why, despite this, it had underspent its budget for capital maintenance by £24 million. HMPPS told us that its maintenance programmes relied on certainty of funding across several years in order to go ahead, and that the rising prison population meant that the programmes were more complex to schedule. It told us that it was working hard to put any underspends into prison maintenance and that the £156 million additional funding secured from government would help bring more cells back into use. It assured us that the funding available for this year would stabilise the prison estate so that it would not continue to lose 500 places per year.18 We similarly asked the Ministry what its plans were to tackle the £900 million maintenance backlog that had built up across the estate. The Ministry accepted that major investment in maintenance within the prison estate was needed to improve conditions, and told us that it was starting work on this.19
Government Response
Not Addressed
HM Government
Not Addressed
4.1 The government agrees with the Committee’s recommendation. Target implementation date: April 2021 4.2 The department will publish prison population projections by the end of 2020 and, following this, will be in a position to forecast how the prison population is likely to change in the coming years. The projections will reflect the impact on demand as a result of various factors, including court recovery. 4.3 New prisons at Wellingborough (to be named HMP Five Wells) and Glen Parva are on track, and the 10,000 prison spaces build programme is set to be delivered by 2026. The department is continually assessing its strategy for managing COVID-19 in the prison estate based on the latest scientific advice. By April 2021, the department will provide an update on progress, including on plans for expected use of temporary accommodation.