Recommendation 18

18

The Department told us that it is working at pace to agree the funding that...

Conclusion
The Department told us that it is working at pace to agree the funding that will be available for the 13 towns in the first cohort and would like to be able to make decisions in October. But the Department did not want to guarantee it would meet that deadline and warned that it could take up to 12 months to agree business cases and issue final approvals before projects can begin.41 The Department told us that, while it would like to see as many projects as possible happen as quickly as possible, given the nature of construction projects and minor infrastructure works, if they are to happen robustly and safely, it would be some time before we see many projects on the ground.42