54th Report - Afghanistan Response Route Published 14 Nov 2025 Addressed to HM Treasury
Conclusion (the committee's words)
At the time of publication of the NAO’s report, the Department had not provided the NAO with enough evidence to have confidence in the completeness and accuracy of the Department’s cost estimates.62 The Department estimates the total cost of the ARR to be £850 million, of which about £400 million has been spent so far, with £450 million to come. The Department said that it could, in anticipation of the super-injunction being lifted and the resulting parliamentary scrutiny, have accounted for the costs of the ARR separately.63 The Department told us that the overall cost of the ARAP scheme, the Afghan Citizens Resettlement Scheme (ACRS) run by the Home Office and the ARR scheme could be over £5 billion.64 The Department said it was possible that it would be able to provide a more detailed breakdown that would allow the C&AG to give us more assurance about costs. The C&AG expects to produce his next report on Afghan resettlement in the first part of next year.65

From: Public Accounts Committee, 54th Report - Afghanistan Response Route (HC 1391), 14 November 2025

Government response

Latest Treasury Minutes progress report to the Committee of Public Accounts on the Fifty-fourth Report of Session 2024-26

The government responded to the whole report on 4 June 2026 (deadline 14 January 2026).

Read the government's response ↗ Report an error

Treasury minutes: Government response to the Committee of Public Accounts on the Fifty-fourth report from Session 2024-26

Published 19 January 2026.

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government agrees with four of the Committee's recommendations, including six-monthly updates on ARR resettlement from March 2026, and disagrees with the recommendation on separately capturing ARR costs.

  • On updates, the government agrees to write to the Committee every six months from March 2026 until the ARR is complete, though it "may not always be possible to provide a precise breakdown by scheme".
  • On the case working system, it agrees, stating the recommendation is implemented and that DACS (introduced in May 2022) addressed "many of the vulnerabilities", with the department "equipped with the right tools to minimise the risk" of a recurrence.
  • On scrutiny, it agrees and gives a target date of Spring 2026. The Treasury will issue a Dear Accounting Officer letter on sharing information with the Comptroller and Auditor General in the event of a super-injunction.
  • It disagrees on separate ARR costing, saying this would be "disproportionately complex and resource intensive", and instead offers an indicative cost allocation at the end of each financial year, included with the six-monthly updates.