Select committee: Public Accounts Committee
Recommendation 25
62nd Report - Faulty energy efficiency installations
Published 23 Jan 2026
Addressed to HM Treasury
Public Accounts Committee Faulty energy efficiency installations All items in this report Report on parliament.uk ↗ Inquiry on parliament.uk ↗
Recommendation (the committee's words)
The Department told us that the Ministers are very clear these problems must be fixed at no cost to households who have done nothing wrong. It told us it expects only a “very small number” of homes to not be remediated by the original installer or covered by the guarantee. The Department told us it is “working hard to drive the system so that all parties come together” to identify bespoke solutions for these most challenging cases.52 We call on the Government where all other avenues have been exhausted to step in and ensure the defects are remediated even though they have now closed this scheme.
From: Public Accounts Committee, 62nd Report - Faulty energy efficiency installations (HC 1229), 23 January 2026
Government response
The government responded to the whole report on 7 April 2026 (deadline 23 March 2026).
Summary written by Accountability Index from the government's response. It is not the government's own words.The government agrees with most of the Committee's recommendations, but disagrees with the recommendation to halt wall insulation installation without independent supervision and with the recommendation to refer fraud to the Serious Fraud Office.
- On wall insulation, it disagrees with the recommendation, noting that every household with external wall insulation under ECO4 and GBIS "is being and will be offered an on-site audit", subject to the householder accepting; internal wall insulation concerns are triaged and referred for audit where they meet "the threshold of risk factors".
- It agrees on the find-and-fix programme: TrustMark "currently intend" it to complete by May 2027, though the department states it is "unlikely" to deliver on a "significantly shorter timescale". It will update the Committee in writing every six months, first in June 2026.
- It disagrees with referring fraud across ECO to the Serious Fraud Office, stating that this "relates to an existing ongoing responsibility of the regulator", Ofgem, which can and does make referrals where appropriate.
- It agrees to publish an annual report to Parliament on retrofit schemes, with the first publication "before Autumn 2027", and "intends to consult" on the design of a reformed consumer protection system during summer 2026.